Atlanta Watershed Management Water Meter & Sewer Fees (2026)

Last reviewed: By Utility Cost Guide editor

Inside Atlanta city limits, the City of Atlanta Department of Watershed Management (DWM) provides both water and sewer. A new single-family home with a 3/4-inch meter installed by the city pays about $2,295 in official one-time charges: $1,200 for the water meter installation, a $600 sewer capacity certification fee, $230 for sewer plan review and site inspection, a $250 sewer connection inspection and a $15 account fee (Atlanta Code, Appendix B – Fees; ATL311, Cost of Permit for Sewer Connection). An $80 refundable deposit is due when you open the account. Atlanta has no separate water or sewer impact fee. The city repealed those in 1995. The biggest caveat is the meter price: the codified schedule is dated October 1, 2015, and DWM does not post prices online, so get an invoice before you budget.

Atlanta connection fees at a glance

The table below lists every Atlanta row we recorded, with its source. It covers two kinds of charge. The water meter installation fee is DWM’s price for the meter itself, the tap on the main and the service line from the right-of-way to your property line (City Code Sec. 154-68). The code lists two city-installation prices per small meter (RR-SS and RR-LS) and a lower price when a private contractor installs. The sewer charges are permit and certification fees, not a capacity buy-in like a Texas impact fee. The meter rows are marked needs-review because of the 2015 date; the sewer rows match an ATL311 article updated in February 2025.

ServiceCategoryFeeMeterAmountBasisEffectiveSourceVerified
General — Account Setup
GeneralAccount SetupAccount establishment fee—$15flat fee—Official source2026-09-24
General — Permit
GeneralPermitRight-of-way construction permit for sewer, water line or meter installation (Sec. 138-65)—$85flat fee—Official source2026-09-25
Sewer — Capacity
SewerCapacitySewer capacity certification fee—$600flat fee—Official source2026-09-25
Sewer — Connection
SewerConnectionCity-constructed sewer connection (minimum)—$5,930varies—Official source2026-09-25
Sewer — Inspection
SewerInspectionInspection of privately constructed sewer connection (single-family)—$250flat fee—Official source2026-09-25
Sewer — Permit
SewerPermitSewer connection permit: plan review and site inspection—$230flat fee—Official source2026-09-25
Water — Deposit
WaterDepositWater service deposit3/4"$80by meter size—Official source2026-09-24
Water — Main Extension
WaterMain ExtensionWater main installation/extension application fee (City Code 154-67)—$2,000flat fee—Official source2026-09-24
Water — Meter
WaterMeterWater meter installation fee, private installation, 1"
Private contractor installs; meter fee
1"$400by meter size2015-10-01Official source2026-09-25 Confirm with utility
WaterMeterWater meter installation fee, private installation, 3/4"
Private contractor installs; meter fee
3/4"$400by meter size2015-10-01Official source2026-09-25 Confirm with utility
Water — Tap
WaterTapWater meter installation fee, city installation, 1" RR-LS
City installs, RR-LS
1"$2,300by meter size2015-10-01Official source2026-09-25 Confirm with utility
WaterTapWater meter installation fee, city installation, 1" RR-SS
City installs, RR-SS
1"$1,400by meter size2015-10-01Official source2026-09-25 Confirm with utility
WaterTapWater meter installation fee, city installation, 3/4" RR-LS
City installs, RR-LS
3/4"$2,000by meter size2015-10-01Official source2026-09-25 Confirm with utility
WaterTapWater meter installation fee, city installation, 3/4" RR-SS
City installs, RR-SS
3/4"$1,200by meter size2015-10-01Official source2026-09-25 Confirm with utility
The water meter prices come from a table in the Code of Ordinances headed “Meter Installation Fees 10/1/2015.” It is still the codified schedule in the August 2026 code update. However, DWM’s meter purchase page says only that “the cost of the meters varies” and that you pay from an invoice. Treat $1,200 as a starting estimate until Meter Applications quotes your address.

Worked example for a single-family home in Atlanta

Assumptions: one detached house on a lot inside city limits that has never been connected to city sewer, a 3/4-inch domestic meter, and no irrigation meter. The schedule gives two city-installation prices for this size: RR-SS at $1,200 and RR-LS at $2,000. On the 3/4-inch rows the code labels them “short body” and “long body” and gives no further explanation. Ask DWM which price applies to your lot.

City of Atlanta one-time charges for one house, 3/4-inch meter (sources: Atlanta Code, Appendix B – Fees, meter rows need review; ATL311 sewer permit costs; DWM Start My Service).

Charge A. City installs, RR-SS B. City installs, RR-LS C. Private contractor installs
Water meter installation fee $1,200 $2,000 $400
Sewer capacity certification $600 $600 $600
Sewer plan review and site inspection $230 $230 $230
Sewer connection inspection (new tap) $250 $250 $250
Account establishment fee $15 $15 $15
Total official charges $2,295 $3,095 $1,495
Refundable deposit $80 $80 $80

The arithmetic: scenario A is $1,200 + $600 + $230 + $250 + $15 = $2,295. Scenario B swaps in the $2,000 RR-LS price, giving $3,095. Scenario C uses the $400 private-installation price, giving $1,495. It looks lowest, but your contractor’s price for the tap and service line comes on top, plus an $85 right-of-way construction permit if the contractor digs in the street. A 1-inch meter adds $200 to scenario A ($1,400) and $300 to scenario B ($2,300); the private-installation price stays $400, and the deposit rises to $140.

Two situations change the sewer side. If the lot was connected to city sewer before, for example a teardown and rebuild, ATL311 says the $600 capacity certification applies to properties “not previously connected,” so it may not apply. If the lot sits in a capacity-limited sewer basin, DWM can require a capacity analysis. The optional flat analysis costs $2,245, and modeling beyond that is billed at actual cost.

What is not included in Atlanta fees

DWM installs the meter in the right-of-way. The DWM meter page says connecting your private water line to the meter is the customer’s job. On the sewer side, ATL311 says the listed prices exclude installation by a qualified contractor, and the owner pays for the sewer tap. So most of the real cost is private work:

The ranges come from our national benchmark set, not from Atlanta sources. See our guides to water service line cost, sewer lateral cost and tap fees vs. impact fees. Add the private work to the Atlanta fees with the calculator:

Estimate utility connection costs

Estimates are planning figures, not quotes. Confirm fees and trench rules with your utility.

Location and property
Services and site work

Many codes require horizontal separation between water and sewer. This estimate assumes separate water and sewer trenches unless you select a shared run where your utility allows it.

Quoted fees and comparison assumptions

How and when Atlanta fees are paid

For a meter 2 inches or smaller on a single house, you file one application per meter with DWM Meter Applications and wait for an invoice. DWM says payments made before the invoice will likely be returned. Payment is due within 14 days of the application, and the meter must be paid in full before installation. The DWM meter purchase page then asks you to allow 15 weeks for installation. Inside the city you must show a City of Atlanta building permit for a domestic meter, and you pay a separate right-of-way fee to the city’s Department of Public Works/Office of Transportation. Contractor self-installations need a plan review by the DWM Office of Engineering Services first. Only the owner or the owner’s designated representative can buy a meter.

On the sewer side, the $230, $600 and $250 charges come with the sewer connection permit through DWM Site Development. If a city crew has to build the sewer connection, the code bills time and materials, with a minimum of $5,930. The $2,000 application fee for a new or extended water main applies only when the city must build a main, not to an ordinary lot on an existing street.

What could change in Atlanta

The main risk is an update to the meter schedule. The codified table is dated October 1, 2015. The next table in the same appendix shows “current” and “proposed” prices for re-establishing old meters, and some proposed prices are far higher: $1,405 instead of $86 for a 3/4-inch meter. We found no adopted increase for new meter installations, but an invoice is the only reliable number. The sewer figures match between the code and the ATL311 article updated February 26, 2025.

Common questions about Atlanta fees

How much are water and sewer tap fees for a new house in Atlanta?

For a 3/4-inch meter installed by DWM, the official charges come to about $2,295: $1,200 for the meter, $600 for sewer capacity certification, $230 for sewer plan review and site inspection, $250 for the sewer inspection and a $15 account fee. The meter price comes from a 2015 schedule, so confirm it with DWM. With the higher RR-LS meter price, the total is $3,095.

Does Atlanta charge a water or sewer impact fee?

No. Ordinance 1995-79 repealed the city’s water and wastewater connection fee chapters in January 1995 and ordered refunds of fees collected since January 1, 1994. Atlanta’s development impact fees now cover transportation, parks, fire and police, not utilities.

How long does it take to get a new water meter in Atlanta?

DWM says to allow 15 weeks after payment. Payment is due within 14 days of your application and only after Meter Applications sends an invoice. You also need a City of Atlanta building permit for the domestic meter.

Who installs the sewer tap in Atlanta?

Usually a qualified contractor you hire. ATL311 says the owner or developer pays for the tap installation, and work in the street needs a right-of-way permit. The codified construction permit for sewer, water line or meter work is $85. If city crews build the connection instead, the minimum charge is $5,930.

What deposit does Atlanta require for new water service?

City Code Sec. 154-114 sets the deposit at $80 for a 3/4-inch meter and $140 for meters from 1 to 2 inches. DWM also charges a $15 account establishment fee when you open the account.

Does this apply to every address with an Atlanta mailing address?

No. These are City of Atlanta fees for property inside city limits. DWM’s meter page notes that properties outside the city need a building permit from their own municipality and a Fulton County sewer permit. Addresses served by DeKalb County or Fulton County utilities pay those counties’ fees, which this page does not cover.

Where to go next from Atlanta

In the Tennessee Valley, Huntsville Utilities tap and sewer access fees and KUB tap and connection fees in Knoxville also list gas and electric charges.

Compare Atlanta with other Southeast cities: Charlotte tap fees, Nashville tap fees, Charleston tap fees and Tampa tap fees, or browse the national tap fees by city table. Background reading: water meter installation cost, sewer tap fee and utility costs for new construction. For the full budget, use the utility connection cost calculator.

Official documents behind the Atlanta figures