Nashville Metro Water Services Tap & Capacity Fees (2026)

Last reviewed: By Utility Cost Guide research team

Metro Water Services (MWS), the utility of the Metropolitan Government of Nashville and Davidson County, charges a new home two kinds of one-time fees under the Metro Code: small flat tap fees and much larger capacity charges. The tap fees are $500 for a 5/8-inch water tap and $360 for a 4- or 6-inch sewer connection. The capacity charges are $1,375 (water) and $2,300 (sewer) per unit of flow, where one unit equals 350 gallons per day (Metro Code 15.20, 15.36). If a house is assessed one unit, the code fees total $4,535. At two units they total $8,210. The caveat that matters most: MWS sets the number of units assigned to a single-family home administratively, and we could not confirm it from a published source, so get that number in writing before you budget.

Official fees at a glance

The rows below come straight from the Metro Code, the ordinance text that sets these fees. The tap amounts were set by Ordinance BL2019-45. The code does not print an effective date or fiscal year next to each fee. Two points help when reading the table. First, the code’s sizes are tap sizes, and the three smallest water taps sit close together ($500, $525, $550). Second, the two capacity charges are listed as a price per unit, not per house. They are the bulk of the bill, and their total depends on the unit count MWS assigns.

ServiceCategoryFeeMeterAmountBasisEffectiveSourceVerified
Sewer — Capacity
SewerCapacitySewer Capacity Charge (Metro Code 15.36.040)$2,300per unitOfficial source2026-09-24
Sewer — Tap
SewerTapSewer Connection Fee (Metro Code 15.36.020)$360flat feeOfficial source2026-09-24
Water — Capacity
WaterCapacityWater System Capacity Charge (Metro Code 15.20.045)$1,375per unitOfficial source2026-09-24
Water — Tap
WaterTapWater Tapping Fee (Metro Code 15.20.030)1"$550by meter sizeOfficial source2026-09-24
WaterTapWater Tapping Fee (Metro Code 15.20.030)3/4"$525by meter sizeOfficial source2026-09-24
WaterTapWater Tapping Fee (Metro Code 15.20.030)5/8"$500by meter sizeOfficial source2026-09-24

What the table does not show: MWS also publishes a development fee schedule with meter, inspection and review charges. That PDF blocked our automated access when we checked on September 24, 2026, so those amounts are not in our database yet. Expect them on top of the code fees.

Worked example: a new single-family home

The per-house formula from the code is simple once you know the unit count:

Code fees = water tap + sewer connection + units × ($1,375 + $2,300)

With a 5/8-inch tap that becomes $500 + $360 + units × $3,675 = $860 + (units × $3,675). Because the unit count for a single-family home was not published where we could read it, here are three cases side by side.

Metro Nashville code fees for one house with a 5/8-inch water tap and a 4-inch sewer connection, by assessed capacity units (source: Metro Code 15.20 and 15.36). Meter and inspection fees not included.

Charge 1 unit (350 gpd) 1.5 units (525 gpd) 2 units (700 gpd)
Water tapping fee (5/8″) $500 $500 $500
Sewer connection fee (4″) $360 $360 $360
Water capacity charge ($1,375/unit) $1,375 $2,062.50 $2,750
Sewer capacity charge ($2,300/unit) $2,300 $3,450 $4,600
Total $4,535 $6,372.50 $8,210

The cases are illustrations of the formula, not MWS determinations. Each extra unit adds $3,675, so the unit count swings the bill far more than the choice between a 5/8-inch ($500) and a 1-inch ($550) tap. If a home reuses an existing tap of the same or smaller size, the code says no new tapping fee is charged. Ask MWS how prior capacity is credited in that case.

What these fees don’t include

The code fees cover the utility’s tap and capacity. The pipe on your property is private work:

For example, a 50-foot water line at $50 and a 50-foot lateral at $100 add about $7,500 before trenching. These are from our national benchmark set. See water service line cost and trenching cost for detail, and model your lot here:

Estimate utility connection costs

Estimates are planning figures, not quotes. Confirm fees and trench rules with your utility.

Location and property
Services and site work

Many codes require horizontal separation between water and sewer. This estimate assumes separate water and sewer trenches unless you select a shared run where your utility allows it.

Quoted fees and comparison assumptions

How and when you pay

Changes to watch

The tap amounts in the code date from Ordinance BL2019-45, and the code does not show a later revision for them. Current cost changes are more likely to show up in the unit count MWS assigns and in its separate fee schedule. Metro’s Development Services fee schedule, dated January 2025 by its file name (DS fee schedule PDF), is the likeliest place for newer charges. We could not open it on September 24, 2026, so we have not used any figure from it. We will add its rows once we can read and verify them.

Before you sign a lot contract in Davidson County, ask MWS for a written fee estimate that states the capacity units assigned to your plans. That one number moves the total by $3,675 per unit.

Frequently asked questions

How much are water and sewer tap fees in Nashville?

The Metro Code tap fees are small: $500 for a 5/8-inch water tap and $360 for a 4- or 6-inch sewer connection. Most of the cost is capacity: $1,375 for water and $2,300 for sewer per 350-gallon-per-day unit.

What is a capacity unit in Nashville?

Metro Water Services prices capacity in units of 350 gallons per day. A single-family home’s unit count is set by MWS. At one unit, capacity charges are $3,675. At two, $7,350.

When are Nashville capacity fees due?

The water capacity charge must be paid before MWS issues the service-connection permit. Plan to pay the capacity charges before construction reaches the connection stage.

Can I pay Nashville capacity fees over time?

The Metro Code has a 36-month, no-interest payment plan, but it excludes single-family developments. Unpaid tap and capacity fees become a lien on the property.

Do I pay a new tap fee if I rebuild on the same lot?

The code waives the water tapping fee when an existing tap of the same or smaller size is reused. Capacity treatment for a rebuild is not spelled out in the sections we reviewed, so ask MWS.