Washington Utility Connection Costs (2026): Tap Fees by City

Last reviewed: By Utility Cost Guide editor

Washington’s three largest utilities in our database charge very different amounts to connect a new single-family home in 2026, and the totals aren’t fully apples-to-apples because each city publishes a different piece of the number. Spokane’s published general facilities charges (GFCs) plus permits come to $8,642 for a 5/8-inch meter, but the city’s own tap and meter installation charge is set separately each year and we could not obtain the 2026 amount, so that total is incomplete. Tacoma’s published water and wastewater system development charges (SDCs) plus its water tap charge come to $9,243, also at a 5/8-inch meter, but the wastewater SDC is only published at that size, and the physical sewer connection for new construction is billed as a share of the building permit’s valuation rather than a flat fee, so no single number covers it. Seattle publishes a complete figure starting at 3/4 inch, the smallest meter it lists: $14,630 on a non-arterial street or $16,005 on an arterial one, before its separate drainage SDC. Our database covers Seattle Public Utilities, the City of Spokane, and Tacoma Water and Environmental Services so far. Other Washington utilities are not yet collected, and we say so rather than guess.

Official fees in Washington

The table below lists every verified Washington fee row in our database, with utility, meter size, effective date and a link to the source document. Washington cities use different names for the same two kinds of one-time charge. The first pays for a share of existing system capacity: Seattle and Tacoma both call it a system development charge (SDC), and Spokane calls it a general facilities charge (GFC). The second pays for the physical work of making the connection: Seattle calls it a water service installation, Tacoma a water service construction charge, and Spokane a tap and meter charge that its code does not fully publish. All three cities size at least the capacity charge by water meter size.

CityProviderWater typical new home*Sewer typical new home*
SeattleSeattle Public Utilities$11,700$2,600
SpokaneCity of Spokane Public Works (Water and Wastewater)$3,475$4,887
TacomaTacoma Power (Tacoma Public Utilities)$5,904$3,339

* Simplified sum of default official residential fees for a standard meter and one unit where applicable. Confirm your actual charges with the utility.

City comparison

Published 2026 water + wastewater one-time charges for one new single-family home, at the smallest meter size each utility publishes a complete figure for (sources: city pages linked below).

City Local term Meter Capacity charge(s) Tap / install charge Total (published)
Seattle System development charge 3/4″ $9,500 ($6,900 water + $2,600 wastewater) $5,130 ($4,800 install + $330 meter, non-arterial) $14,630
Spokane General facilities charge 5/8″ $8,362 ($3,475 water + $4,887 wastewater) $280 ($65 tap/meter application + $215 side sewer permit) $8,642 (tap/meter charge itself not published)
Tacoma System development charge 5/8″ $4,543 ($1,204 water + $3,339 wastewater) $4,700 (water service construction charge) $9,243 (excludes the valuation-based sewer connection fee)

How the totals are built. Seattle: $6,900 water SDC + $2,600 wastewater SDC + $4,800 water service installation + $330 meter = $14,630 on a non-arterial street; on an arterial street the installation charge rises to $6,175, for $16,005. Spokane: $3,475 water GFC + $4,887 wastewater GFC + $65 tap and meter application + $215 side sewer permit = $8,642; the city’s actual tap and meter charge is set in a yearly public rule we could not access, so the true total is higher. Tacoma: $1,204 water SDC + $4,700 water service construction charge + $3,339 wastewater SDC = $9,243; the side sewer connection is billed separately, either as a flat $580 permit (for reconnecting an existing house) or, for a new single-family home, as 65% of the building permit fee plus 45% for plan review, both scaled to the home’s ICC valuation, so it can’t be reduced to one number here.

On the pieces that are published and genuinely comparable, Tacoma’s capacity charges are the lowest of the three: $4,543 combined water and wastewater SDC, against $8,362 in Spokane and $9,500 in Seattle at Seattle’s 3/4-inch minimum. Seattle’s $5,130 tap-and-meter charge is close to Tacoma’s $4,700 water tap charge; Spokane does not publish a comparable figure at all, which is why its $8,642 total understates the real cost.

City pages with the full fee rows, payment timing and local caveats: Seattle Public Utilities SDCs and water tap costs, Spokane general facilities charges and tap fees, and Tacoma water and sewer tap and connection fees.

What decides your number

Seattle, Spokane and Tacoma are the only Washington utilities in our database so far. Other Washington cities and districts may use the same SDC or GFC terminology, or different terms entirely, and their fees are not yet collected here.

Costs beyond the utility’s fees

None of the three cities’ published totals above cover the private work between the utility’s connection and the house, and in Spokane and Tacoma part of the utility’s own charge is missing too. For a full budget, add these national estimates, not Washington figures (methodology):

Worked example: a Tacoma infill lot with the house 50 feet from the street. The published utility fees are $9,243. Typical private work adds 50 × $50 = $2,500 (water line) + 50 × $100 = $5,000 (side sewer) + $300 (permit), for a planning total near $17,043, before whatever the valuation-based site development fee adds on top. Run your own lot through the calculator:

Estimate utility connection costs

Estimates are planning figures, not quotes. Confirm fees and trench rules with your utility.

Location and property
Services and site work

Many codes require horizontal separation between water and sewer. This estimate assumes separate water and sewer trenches unless you select a shared run where your utility allows it.

Quoted fees and comparison assumptions

Frequently asked questions

How much are water and sewer tap fees in Washington?

It depends entirely on the utility. For 2026, published charges for a new single-family home run from $8,642 in Spokane (5/8-inch meter, capacity charges plus permits; the tap and meter charge itself isn’t published) to $9,243 in Tacoma (5/8-inch meter) to $14,630-$16,005 in Seattle (3/4-inch meter, depending on whether the street is an arterial).

What is a system development charge in Washington?

It’s a one-time charge for capacity in a utility’s existing water and sewer systems, separate from the physical cost of the connection. Seattle and Tacoma call it a system development charge (SDC). Spokane’s version is called a general facilities charge (GFC); it works the same way.

Which Washington city has the lowest utility connection costs?

Among the three cities we’ve verified, Tacoma’s published capacity charges are the lowest: $4,543 combined water and wastewater SDC at a 5/8-inch meter, against $8,362 in Spokane and $9,500 in Seattle’s 3/4-inch minimum. But Tacoma’s total is incomplete, since its sewer connection is billed as a share of the building permit valuation rather than a flat fee, so the real cost for a specific house could be higher.

Does meter size change the fee in these Washington cities?

Yes, in all three. Seattle’s water and wastewater SDCs multiply by 1.7 going from 3/4 inch to 1 inch, adding $6,650. Tacoma’s water SDC rises from $1,204 to $2,972 at 1 inch. Spokane’s combined water and wastewater GFC rises from $8,362 at 5/8 inch to $20,904 at 1 inch.

Related pages

Other state hubs: Colorado, Arizona, North Carolina and Utah. City pages: Seattle, Spokane and Tacoma. Guides: tap fee vs. impact fee, cost to bring utilities to land, utility costs for new construction and tap fees by city.

Sources