Sarasota County Water & Sewer Capacity Fees (2026)

Last reviewed: By Utility Cost Guide editor

In unincorporated Sarasota County, water and sewer usually come from Sarasota County Public Utilities, and its connection charges are set countywide rather than by zone. For a new single-family home with the standard 5/8-inch meter, the charges in Resolution 2026-211 (adopted August 25, 2026) are $4,250 (water facilities capacity fee) + $4,480 (wastewater facilities capacity fee) + $215.17 (meter installation) + $40 (building permit review fee) = $8,985.17. The main caveat is the lot: if it connects to water and sewer lines the county itself built or bought, the county adds line extension fees of $1,000 and $1,500 per equivalent dwelling unit, which brings the total to $11,485.17. For how this compares nationally, see our guide to the cost to connect to city water.

Sarasota County connection fees at a glance

All current figures come from Resolution 2026-211, which replaced Resolution 2025-249. The capacity fees are in Exhibit B, the meter and line-extension charges in Exhibit A, and the $40 review fee in Exhibit C. Capacity fees and line extension fees are charged per equivalent dwelling unit (EDU). On the county’s EDU form, a detached, individually metered house counts as 1.00 EDU. A house of 750 square feet or less counts as 0.50. The table marks which rows a typical new house pays. Rows that apply only to certain lots are listed separately. The $15 account fee and the refundable deposit are listed too, but they are not part of the connection totals.

ServiceCategoryFeeMeterAmountBasisEffectiveSourceVerified
General — Account Setup
GeneralAccount SetupAccount Application/Transfer Fee—$15flat fee2026-08-25Official source2026-09-25
General — Deposit
GeneralDepositSecurity Deposit, Individually Metered Residential (water $75 + wastewater $75)—$150flat fee2026-08-25Official source2026-09-25
General — Permit
GeneralPermitBuilding Permit Review Fee (utility capacity fee review)—$40flat fee2026-08-25Official source2026-09-24
Sewer — Capacity
SewerCapacityCurry Creek Wastewater Capacity Fee Component—$187.65per equivalent residential unit2026-08-25Official source2026-09-24
SewerCapacityWastewater Facilities Capacity Fee—$4,480per equivalent residential unit2026-08-25Official source2026-09-24
Sewer — Main Extension
SewerMain ExtensionWastewater Line Extension Fee—$1,500per equivalent residential unit2026-08-25Official source2026-09-24
Sewer — Other
SewerOtherWastewater Lateral Locate Charge (field locate and flag)—$50flat fee2026-08-25Official source2026-09-24
Water — Capacity
WaterCapacityWater Facilities Capacity Fee—$4,250per equivalent residential unit2026-08-25Official source2026-09-24
Water — Main Extension
WaterMain ExtensionWater Line Extension Fee—$1,000per equivalent residential unit2026-08-25Official source2026-09-24
Water — Meter
WaterMeterNew Water Service - Meter Installation Fee
1 1/2-inch meter
1 1/2"$587.23by meter size2026-08-25Official source2026-09-24
WaterMeterNew Water Service - Meter Installation Fee
1-inch meter
1"$300.69by meter size2026-08-25Official source2026-09-24
WaterMeterNew Water Service - Meter Installation Fee
2-inch meter
2"$638.70by meter size2026-08-25Official source2026-09-24
WaterMeterNew Water Service - Meter Installation Fee
5/8-inch meter (standard)
5/8"$215.17by meter size2026-08-25Official source2026-09-24

Worked example: a new home in Sarasota County

Assumptions: one detached house of 751 to 5,000 square feet of living space (1.00 EDU), its own 5/8-inch meter, gravity sewer, a lot in a subdivision whose water and sewer lines were built by the developer, and a building permit issued under Resolution 2026-211.

Sarasota County Public Utilities one-time charges for one house (source: Resolution 2026-211).

Charge Developer-built lines County-built lines
Water facilities capacity fee (1 EDU) $4,250.00 $4,250.00
Wastewater facilities capacity fee (1 EDU) $4,480.00 $4,480.00
Meter installation, 5/8 inch $215.17 $215.17
Building permit review fee $40.00 $40.00
Water line extension fee (1 EDU) n/a $1,000.00
Wastewater line extension fee (1 EDU) n/a $1,500.00
Total $8,985.17 $11,485.17

Developer-built lines: $4,250 + $4,480 + $215.17 + $40 = $8,985.17. County-built lines: $8,985.17 + $1,000 + $1,500 = $11,485.17. The resolution applies the line extension fees to new customers who connect to “existing water distribution lines purchased or constructed by the Utility.” It doesn’t list which streets those are, so ask the Utilities Connection office (941-861-6767) before you budget.

Three other things change the math:

When you open the account, Resolution 2026-211 also lists a refundable deposit of $75 for water and $75 for wastewater and a $15 account application fee. The deposit can be waived for an owner of the property who passes the identity check and has a satisfactory payment history. These are account charges rather than connection fees, so they are left out of the totals above.

What is not included in Sarasota County fees

The county’s fees cover system capacity and the meter. It does not charge a fixed tap fee. If county crews have to tap the main and run the service to the property line, Resolution 2026-211 bills that work at actual cost for both water and wastewater. Everything on the private side of the meter or cleanout is paid by the owner:

At 40 feet from the street, that works out to roughly 40 × $50 = $2,000 for water and 40 × $100 = $4,000 for sewer (national benchmarks, not county figures). On a low-pressure sewer system, the county supplies and installs the single-family pressure (grinder) unit at actual cost. The owner then runs the on-site line and brings the unit a properly rated electrical supply. See grinder pump connection costs. You can enter your own figures in the calculator:

Estimate utility connection costs

Estimates are planning figures, not quotes. Confirm fees and trench rules with your utility.

Location and property
Services and site work

Many codes require horizontal separation between water and sewer. This estimate assumes separate water and sewer trenches unless you select a shared run where your utility allows it.

Quoted fees and comparison assumptions

When you pay Sarasota County connection fees

Septic-to-sewer: Phillippi Creek program

The county’s Phillippi Creek Septic System Replacement Program has been installing central sewer since 2001. It is expected to eliminate about 14,000 septic tanks. Properties inside the project boundaries are charged a non-ad valorem assessment on the property tax bill once the work is done. Resolution 2026-211 also sets a monthly wastewater surcharge of $19 per EDU for 240 billing periods, to recover the rest of the owner’s share of the sewer cost that the assessment doesn’t cover. The Utility Deferred Payment Assistance Program ((941) 500-2476) helps with payment. If you have a septic tank in a project area, ask the Utilities Connection office what you still owe before you compare with the new-construction totals above.

How Sarasota County compares in Florida

At $8,985.17, the typical county total is higher than Fort Myers ($7,017.40 on city water and sewer) and Cape Coral ($7,571 on a served lot). It is lower than Port St. Lucie ($12,427 on a gravity-sewer lot) and unincorporated Hillsborough County’s South/Central area ($10,530.75). The Hillsborough Northwest area comes to $7,503.25. Those figures come from our Fort Myers, Cape Coral, Port St. Lucie and Hillsborough County pages, each for its own standard case. Sarasota’s rate is one countywide number, while Hillsborough’s depends on service area.

A Sarasota County address does not always mean county water. Some cities in the county run their own utilities, and private franchise utilities serve some areas. County capacity fees still apply where the county sells water wholesale to a franchise. Use the county’s service availability inquiry form or call 941-861-6767 to check which utility serves your parcel.

Sarasota County fee changes to watch

Sarasota County connection fee questions

How much are water and sewer capacity fees in Sarasota County?

Under Resolution 2026-211, the water facilities capacity fee is $4,250 and the wastewater facilities capacity fee is $4,480 per equivalent dwelling unit. A typical single-family house is 1.00 EDU, so it pays $8,730 in capacity fees. With the $215.17 meter and $40 review fee, the total is $8,985.17.

Are Sarasota County capacity fees the same as impact fees?

Yes. The resolution says capacity fees were “previously known as impact fees.” They pay a new connection’s share of treatment, storage and transmission capacity. They are separate from road, school and other county impact fees charged on a building permit.

When do I pay Sarasota County utility capacity fees?

Before the building permit is issued. You submit the notarized EDU Conversion Table form with the permit application, along with the $40 review fee. The utility offers financing for the capacity fees.

What is the Sarasota County line extension fee?

It is $1,000 per EDU for water and $1,500 for wastewater. The resolution applies it to new customers who connect to existing lines the utility bought or built. It doesn’t list those lines, so ask the Utilities Connection office (941-861-6767) whether your lot is on one.

Do Sarasota County fees apply inside the cities?

Only if Sarasota County Public Utilities serves the parcel. Some cities in the county run their own utilities with their own fees. The county’s fees apply to parcels it serves, including franchise utility areas the county supplies wholesale. Call 941-861-6767 to confirm which utility serves your lot.

How much does a septic-to-sewer conversion cost in Sarasota County?

In the Phillippi Creek program area, owners pay a non-ad valorem assessment on the tax bill. Resolution 2026-211 adds a $19 monthly surcharge per EDU for 240 bills. The county doesn’t publish a single assessment amount, so ask the Utilities Connection office for your parcel.

More on Sarasota County and nearby cities

Florida utility connection costs · Hillsborough County fees · Fort Myers fees · Tap fee vs. impact fee · Why tap fees are going up · Utility connection cost calculator

Sources for Sarasota County figures