Cape Coral Water, Sewer & Irrigation Connection Fees (2026)
The City of Cape Coral runs all three utility systems a new house can connect to: potable water, wastewater (sewer) and a separate non-potable irrigation system. On a lot whose lines are already in and paid for, a new single-family home with the standard 5/8-inch meter pays $1,520 (water, dual service) + $2,636 (irrigation) + $3,090 (sewer, District 1) in utility capital expansion fees, plus $325 to install the meter: $7,571. In sewer District 2 the same house pays $8,669. The biggest caveat is whether the lot has paid for its lines yet: in a Utilities Extension Project (UEP) area, or on an unassessed lot near existing lines, the city adds a land-area charge of about $25,500 to $26,600 per 10,000 square feet.
Cape Coral tap and connection charges at a glance
The table below lists every Cape Coral charge we verified. The utility capital expansion fees (UCEF) come from the city’s UCEF schedule under Ordinance 12-24, in effect July 27, 2026 through July 26, 2027. Read the water rows as alternatives: you pay the $1,520 dual-service water fee plus the $2,636 irrigation fee where city irrigation is available, or the $3,027 water-only fee where it is not. Sewer has two districts, and you pay one of the two. Rows marked as UEP assessments, CFEC or CIAC apply only to certain lots, as explained below. The meter, deposit and application fees come from the rate schedules effective October 1, 2025.
| Service | Category | Fee | Meter | Amount | Basis | Effective | Source | Verified |
|---|---|---|---|---|---|---|---|---|
| General — Permit | ||||||||
| General | Permit | Plumbing Misc - Miscellaneous Permits Other than New Construction | — | $140 | flat fee | 2026-01-01 | Official source | 2026-09-24 |
| Reclaimed — Capacity | ||||||||
| Reclaimed | Capacity | UEP Capital Facility Expansion Charge (CFEC) - Irrigation | 5/8" | $2,254 | per equivalent residential unit | 2025-11-20 | Official source | 2026-09-24 |
| Reclaimed | Capacity | Utility Capital Expansion Fee - Irrigation Fee | 5/8" | $2,636 | by meter size | 2026-07-27 | Official source | 2026-09-24 |
| Reclaimed — Main Extension | ||||||||
| Reclaimed | Main Extension | Contribution in Aid of Construction (CIAC) - Irrigation | — | $7,710 | per unit | 2025-11-20 | Official source | 2026-09-24 |
| Reclaimed | Main Extension | North 1 East UEP Land Area Assessment - Irrigation | — | $7,710 | per unit | 2025-11-20 | Official source | 2026-09-24 |
| Reclaimed | Main Extension | North 1 West UEP Land Area Assessment - Irrigation | — | $6,041 | per unit | 2023-03-23 | Official source | 2026-09-24 |
| Sewer — Capacity | ||||||||
| Sewer | Capacity | UEP Capital Facility Expansion Charge (CFEC) - Sewer | 5/8" | $3,390 | per equivalent residential unit | 2025-11-20 | Official source | 2026-09-24 |
| Sewer | Capacity | Utility Capital Expansion Fee - Sewer, District 1 Sewer District 1 | 5/8" | $3,090 | by meter size | 2026-07-27 | Official source | 2026-09-24 |
| Sewer | Capacity | Utility Capital Expansion Fee - Sewer, District 2 Sewer District 2 | 5/8" | $4,188 | by meter size | 2026-07-27 | Official source | 2026-09-24 |
| Sewer — Main Extension | ||||||||
| Sewer | Main Extension | Contribution in Aid of Construction (CIAC) - Wastewater | — | $9,607 | per unit | 2025-11-20 | Official source | 2026-09-24 |
| Sewer | Main Extension | North 1 East UEP Land Area Assessment - Sewer | — | $9,607 | per unit | 2025-11-20 | Official source | 2026-09-24 |
| Sewer | Main Extension | North 1 West UEP Land Area Assessment - Sewer | — | $13,330 | per unit | 2023-03-23 | Official source | 2026-09-24 |
| Sewer — Permit | ||||||||
| Sewer | Permit | Septic Abandonment Permit Fee | — | $100 | flat fee | — | Official source | 2026-09-24 |
| Water — Account Setup | ||||||||
| Water | Account Setup | New Account - Application Fee (cover cost of credit check) | — | $20 | flat fee | 2023-03-16 | Official source | 2026-09-24 |
| Water — Capacity | ||||||||
| Water | Capacity | UEP Capital Facility Expansion Charge (CFEC) - Water | 5/8" | $1,106 | per equivalent residential unit | 2025-11-20 | Official source | 2026-09-24 |
| Water | Capacity | Utility Capital Expansion Fee - Water Fee for Dual Service (water with irrigation) City irrigation available (dual service; irrigation fee also due) | 5/8" | $1,520 | by meter size | 2026-07-27 | Official source | 2026-09-24 |
| Water | Capacity | Utility Capital Expansion Fee - Water Only, Fee for Single Service No city irrigation available (water only) | 5/8" | $3,027 | by meter size | 2026-07-27 | Official source | 2026-09-24 |
| Water — Deposit | ||||||||
| Water | Deposit | Security Deposit - Residential | — | $225 | flat fee | 2023-03-16 | Official source | 2026-09-24 |
| Water — Main Extension | ||||||||
| Water | Main Extension | Contribution in Aid of Construction (CIAC) - Potable Water | — | $8,221 | per unit | 2025-11-20 | Official source | 2026-09-24 |
| Water | Main Extension | North 1 East UEP Land Area Assessment - Water | — | $8,221 | per unit | 2025-11-20 | Official source | 2026-09-24 |
| Water | Main Extension | North 1 West UEP Land Area Assessment - Water | — | $7,246 | per unit | 2023-03-23 | Official source | 2026-09-24 |
| Water — Meter | ||||||||
| Water | Meter | Water Meter Installation - 1" Meter | 1" | $430 | by meter size | 2023-03-16 | Official source | 2026-09-24 |
| Water | Meter | Water Meter Installation - 5/8" Meter | 5/8" | $325 | by meter size | 2023-03-16 | Official source | 2026-09-24 |
Worked example for a single-family home in Cape Coral
Assumptions: one detached house, a 5/8-inch meter, fees paid on a building permit issued between July 27, 2026 and July 26, 2027. The lot size only matters in the second and third cases.
(a) A lot already served by paid-for lines
This is a lot in an older part of the city whose water, sewer and irrigation mains were built and assessed years ago. The builder pays only the capacity fees and the meter.
City of Cape Coral charges for one new house, 5/8-inch meter (sources: UCEF schedule, 2026–27; rate schedules).
| Charge | District 1, with irrigation | District 2, with irrigation | District 1, no city irrigation |
|---|---|---|---|
| Water capital expansion fee | $1,520 | $1,520 | $3,027 |
| Irrigation capital expansion fee | $2,636 | $2,636 | n/a |
| Sewer capital expansion fee | $3,090 | $4,188 | $3,090 |
| Meter installation, 5/8 inch | $325 | $325 | $325 |
| Total fees | $7,571 | $8,669 | $6,442 |
| Utility account deposit (waivable) | $225 | $225 | $225 |
District 1 with irrigation: $1,520 + $2,636 + $3,090 + $325 = $7,571. District 2: $1,520 + $2,636 + $4,188 + $325 = $8,669. Water only: $3,027 + $3,090 + $325 = $6,442. A water-only home in District 2 would pay $3,027 + $4,188 + $325 = $7,540. The schedule does not map the two sewer districts; it tells owners to confirm the district number in the city’s IMS site. You can also ask the city’s assessments/impact fee billing line, (239) 242-3852, listed on the Utilities Department page.
A larger meter raises everything: at 1 inch the water-only fee is $7,568, the sewer fee is $7,725 or $10,471, and the meter installation is $430.
(b) A lot in an active UEP area
In a Utilities Extension Project, the city builds the water, sewer and irrigation mains into a neighborhood of wells and septic tanks and assesses each parcel for them by land area. The unit is an equivalent parcel (EP) of 10,000 square feet. Each parcel also pays a Capital Facility Expansion Charge (CFEC) of one equivalent residential unit. The project pages do not say whether the capital expansion fees in case (a) are also due. The city’s new-construction page says those fees are collected on new-construction permits for properties in UEP areas built before the SW 6 & 7 expansion, with some exclusions, so confirm with Customer Billing Services which charge applies to your lot. The totals below assume the CFEC only. Owners leaving a well should also read what switching from a well to city water involves.
UEP charges per 10,000 sq ft parcel with a 5/8-inch meter (sources: North 1 East assessment costs; North 1 West assessment costs).
| Charge | North 1 East | North 1 West |
|---|---|---|
| Assessment: water / sewer / irrigation | $8,221 / $9,607 / $7,710 | $7,246 / $13,330 / $6,041 |
| Assessment per EP | $25,538 | $26,617 |
| CFEC: water / sewer / irrigation | $1,106 / $3,390 / $2,254 | $1,106 / $3,390 / $2,254 |
| CFEC per home | $6,750 | $6,750 |
| Meter installation | $325 | $325 |
| Total, 10,000 sq ft lot | $32,613 | $33,692 |
North 1 East: $25,538 + $6,750 + $325 = $32,613. On a 15,000-square-foot lot (1.5 EP) the assessment is $25,538 × 1.5 = $38,307, so the total is $45,382. An existing home on septic also pays a $100 septic abandonment permit and hires a plumber, which the city estimates at $2,000 to $3,000 on its plumber’s connection cost page. The earlier North 2 project cost $12,632 per EP; see septic-to-sewer conversion cost for that project and its financing.
(c) A lot outside any assessment area, near existing lines
When a lot that was never assessed has city service within 200 feet, the city charges a one-time Contribution in Aid of Construction (CIAC) on development, under Ordinance 108-22. It uses the most recently adopted UEP rates, now North 1 East: $8,221 water, $9,607 wastewater and $7,710 irrigation per EP, or $25,538 for a 10,000-square-foot lot, according to the city’s new construction information page. The page does not say whether the capital expansion fees in case (a) are due on top, so ask Customer Billing Services before you buy such a lot.
What is not included in Cape Coral fees
City charges end at the meter and the right-of-way. Your plumber installs the water line and the sewer lateral from the house to the right-of-way:
- Water service line, installed including the trench: $30 to $150 per foot, about $50 typical (national estimate).
- Sewer lateral, installed including the trench: $50 to $250 per foot, about $100 typical (national estimate).
- Plumbing permit: $100 to $1,300, about $300 typical (national estimate). Cape Coral’s miscellaneous plumbing permit for work outside a new-construction permit is $140 under its January 2026 permit fee schedule. For a new house, plumbing is part of the building permit.
At 30 feet from the right-of-way that is roughly 30 × $50 = $1,500 for water and 30 × $100 = $3,000 for sewer (national benchmarks, not city figures). Electric service is arranged separately and is not in this table. Add your own lengths in the calculator:
Estimate utility connection costs
Estimates are planning figures, not quotes. Confirm fees and trench rules with your utility.
When you pay Cape Coral connection fees
- Capital expansion fees are collected on the new-construction building permit and can be financed over six years on the tax bill at the prime rate plus 1%, plus a 1% administrative fee.
- CIAC can be financed over 15 years on the tax bill on the same interest terms.
- UEP assessments are billed to the parcel, upfront or in annual installments on the tax bill. According to the city’s UEP FAQ, the installments stay with the property when it is sold, so ask for the payoff before closing.
- Meter and deposit. You apply to Customer Billing Services and pay the $325 meter fee and the $225 deposit before the city installs the meter. The deposit is waived with 12 months of good payment history on a city account, a letter of credit from a previous utility, or an Experian utility credit score of 600 or more; the credit check costs $20. The application adds a charge equal to half the meter fee if the house number is not posted or the meter area is not clear.
- UEP deadline. Homes in a finished project must connect to water and sewer within 180 days of the city’s Notice of Availability. Irrigation connection depends on the project; it is currently mandatory in the Mid-Hawthorn Aquifer area. Vacant lots connect when the house is built. See mandatory sewer connection rules.
Upcoming changes in Cape Coral
- July 27, 2027: the current UCEF schedule ends July 26, 2027, so a permit issued after that date may pay different capital expansion fees.
- New UEP projects: North 3 is in design and North 5 and North 6 are under study. The CIAC rate follows the latest adopted UEP rates, so it will change when the next project’s assessment is adopted.
- October 1, 2026: the city has posted rate schedules effective October 1, 2026. They keep the $325 and $430 meter fees, the $225 residential deposit and the $20 application fee.
Cape Coral tap fee FAQ
How much are water and sewer impact fees in Cape Coral?
Cape Coral calls them utility capital expansion fees. For a single-family home with a 5/8-inch meter from July 27, 2026, they are $1,520 for water plus $2,636 for irrigation where city irrigation is available ($3,027 for water alone where it is not), and $3,090 or $4,188 for sewer depending on the district.
What is a UEP assessment in Cape Coral?
It is a special assessment for the water, sewer and irrigation mains the city builds into older neighborhoods. It is charged by land area: $25,538 per 10,000 square feet in North 1 East and $26,617 in North 1 West, plus a $6,750 capacity charge per home.
Do I have to connect to city water and sewer in Cape Coral?
In a finished UEP area, yes: developed properties must connect to water and sewer within 180 days of the Notice of Availability. Irrigation may be optional depending on the project. Vacant lots connect when a house is built.
Can I keep my well for irrigation after connecting?
The well can stay, but the city’s new-construction page says it currently cannot be used as an irrigation water source. The UEP page says this depends on the project, so check your project’s rules.
What does a Cape Coral lot owe if it was never assessed?
If city service is within 200 feet, the city charges a Contribution in Aid of Construction when the lot is developed: $25,538 per 10,000 square feet at current rates, which can be financed over 15 years on the tax bill.
Can the $225 utility deposit be waived?
Yes, with 12 months of good payment history on a prior city account, a letter of credit from a previous utility, or an Experian utility credit score of at least 600. The credit check costs $20.
Related guides for Cape Coral
Across the Caloosahatchee, Fort Myers and Lee County Utilities fees cover the city and the county system side by side.
Florida utility connection costs · Septic-to-sewer conversion cost · Mandatory sewer connection distance · Port St. Lucie tap fees · Hillsborough County impact fees · Utility connection cost calculator
Official documents behind the Cape Coral figures
- Utility Capital Expansion Fees (UCEF), Ordinance 12-24, rates effective 07/27/2026 thru 07/26/2027, City of Cape Coral. Checked Sep 24, 2026.
- Water, Wastewater & Irrigation Rate Schedules, effective October 1, 2025, City of Cape Coral Customer Billing Services. Checked Sep 24, 2026.
- Utility Extension/New Utility Connections: General Information (CIAC, capital expansion fees, UEP connection), City of Cape Coral. Checked Sep 24, 2026.
- North 1 East Assessment Costs, City of Cape Coral Public Works. Checked Sep 24, 2026.
- North 1 West Assessment Costs, City of Cape Coral Public Works. Checked Sep 24, 2026.
- Utilities Extension Project: How to Connect, City of Cape Coral. Checked Sep 24, 2026.
- Plumber’s Connection Costs, City of Cape Coral. Checked Sep 24, 2026.
- Miscellaneous Permit Fee Schedule, effective January 1, 2026, City of Cape Coral Development Services. Checked Sep 24, 2026.
- Water, Wastewater & Irrigation Rate Schedules, effective October 1, 2026, City of Cape Coral Customer Billing Services. Checked Sep 25, 2026.
- Utilities Extension Project: Frequently Asked Questions, City of Cape Coral. Checked Sep 25, 2026.
- Utilities Department contacts, City of Cape Coral. Checked Sep 24, 2026.
- National cost estimates: Utility Cost Guide benchmark methodology.