Salt Lake City Water and Sewer Connection Fees, and the Pending Increase (2026)
Salt Lake City’s Department of Public Utilities provides water, sewer and stormwater service inside the city. A new single-family home with a 3/4-inch meter on a lot of a quarter acre or less pays about $3,080 under the Consolidated Fee Schedule as amended June 16, 2026: a $1,871 water connection fee, a $545 sewer connection fee, a $374 stormwater impact fee and $290 in inspections. That is likely to change. The city has proposed new impact fees that would bring the same home to about $12,130, and they take effect 90 days after the City Council approves them.
Official fees at a glance
All of the rows below come from one document, the Salt Lake City Consolidated Fee Schedule, amended June 16, 2026 by Ordinance 2026-29 for fiscal 2027. The water connection fee is what the city’s impact fee page calls its existing water impact fee; it is priced by meter size and is slightly higher for SLC water customers outside city limits. The sewer connection fee is per dwelling. The stormwater impact fee is charged per quarter acre, which the city treats as one typical residential unit. The two inspection rows cover the new meter and the sewer lateral. Meter hardware and installation are billed at actual cost, so they have no fixed price.
| Service | Category | Fee | Meter | Amount | Basis | Effective | Source | Verified |
|---|---|---|---|---|---|---|---|---|
| Sewer — Connection | ||||||||
| Sewer | Connection | Sanitary Sewer Connection Fee - Residential single dwelling (new development) | — | $545 | per unit | — | Official source | 2026-09-24 |
| Sewer — Inspection | ||||||||
| Sewer | Inspection | Sewer lateral inspection | — | $170 | flat fee | — | Official source | 2026-09-24 |
| Stormwater — Impact | ||||||||
| Stormwater | Impact | Storm Water Impact Fee | — | $374 | per unit | — | Official source | 2026-09-24 |
| Water — Connection | ||||||||
| Water | Connection | Water Connection Fee - Residential single family, City Inside Salt Lake City | 3/4" | $1,871 | by meter size | — | Official source | 2026-09-24 |
| Water | Connection | Water Connection Fee - Residential single family, County County, outside city limits | 3/4" | $1,952 | by meter size | — | Official source | 2026-09-24 |
| Water — Inspection | ||||||||
| Water | Inspection | New Service Meter Install Inspection (3/4" and 1") | 3/4" | $120 | flat fee | — | Official source | 2026-09-24 |
Worked example: a new single-family home
Assumptions: a detached home inside Salt Lake City, on city water and sewer, lot of a quarter acre or less. Meter hardware and installation are extra at actual cost.
Salt Lake City connection charges, current schedule (amended 06/16/2026) vs proposed impact fees
| Charge | Current, 3/4″ | Current, 1″ | Proposed, 3/4″ |
|---|---|---|---|
| Water connection (impact) fee | $1,871 | $3,297 | $5,577 |
| Sanitary sewer connection fee | $545 | $545 | $4,300 |
| Stormwater impact fee (one quarter acre) | $374 | $374 | $1,963 |
| New service meter install inspection | $120 | $120 | $120 |
| Sewer lateral inspection | $170 | $170 | $170 |
| Total before meter at cost | $3,080 | $4,506 | $12,130 |
The proposed column keeps today’s inspection fees, since the proposal we read covers the three impact fees. On that basis the increase for a typical new home would be $12,130 − $3,080 = $9,050. The proposal does not list a 1-inch water figure in the material we recorded, so we did not project the 1-inch column.
Lot size matters through the stormwater fee. Counting a half-acre lot as two quarter-acre units, the current stormwater fee would be 2 × $374 = $748, and the proposed fee 2 × $1,963 = $3,926. Ask the city how it rounds partial quarter acres.
What these fees don’t include
The fee schedule charges for capacity and inspections. The meter hardware and installation are billed at actual cost. The service line from the main, the sewer lateral, excavation, street repair and the building permit are separate. National estimates (methodology):
- Meter set, 5/8″ to 1″: $200–$500, typical $300. Salt Lake City bills its actual cost.
- Water service line: $30–$150 per foot, typical $50. At 50 feet, about $2,500.
- Sewer lateral: $50–$250 per foot, typical $100. At 50 feet, about $5,000.
- Street cut or bore: $1,000–$10,000 per crossing, typical $4,000.
Estimate utility connection costs
Estimates are planning figures, not quotes. Confirm fees and trench rules with your utility.
How and when you pay
Water customers outside city limits who are served by Salt Lake City Public Utilities pay a county rate for the water connection: $1,952 for 3/4 inch and $3,494 for 1 inch, compared with $1,871 and $3,297 inside the city.
Multi-unit homes pay different sewer amounts under the current schedule: $818 for a duplex, $1,226 for a triplex, and $409 per unit for townhouses and apartments. Condominiums and twin-home single dwellings pay the $545 single-dwelling rate.
Changes to watch
- Proposed in July 2026: water impact fee (3/4″) $1,871 → $5,577; sewer $545 → $4,300 per single-family home; stormwater $374 → $1,963 per quarter acre. Effective 90 days after Council approval. We will update this page when the adopted schedule is published.
- The Consolidated Fee Schedule was last amended June 16, 2026 (Ordinance 2026-29). Check it again before paying.
Frequently asked questions
How much is the water connection fee in Salt Lake City?
Under the schedule amended June 16, 2026, it is $1,871 for a 3/4-inch single-family meter inside the city and $3,297 for 1 inch. A proposed increase would raise the 3/4-inch fee to $5,577.
How much does a sewer connection cost in Salt Lake City?
The current sanitary sewer connection fee is $545 per single dwelling, plus a $170 lateral inspection. The city has proposed a sewer impact fee of $4,300 per single-family home.
When will Salt Lake City’s new impact fees take effect?
The proposal says the new fees take effect 90 days after the City Council approves them. As of our September 24, 2026 check, the fee schedule still showed the current amounts.
What is the Salt Lake City stormwater impact fee?
It is $374 per quarter acre under the current schedule; the city treats a quarter acre as one typical residential unit. The proposal would raise it to $1,963 per quarter acre.
Is the meter included in Salt Lake City’s water connection fee?
No. Meter hardware and installation are billed at actual cost, and the new meter installation inspection is a separate $120.
Related pages
tap fees by city · Denver Water tap fees · Las Vegas connection charges · tap fee vs impact fee · sewer tap fee · utility connection cost calculator
Sources
- Consolidated Fee Schedule (amended 06/16/2026, Ord. 2026-29), Salt Lake City Corporation. Checked Sep 24, 2026.
- Impact Fees, Salt Lake City Department of Public Utilities. Checked Sep 24, 2026.