Greeley Water and Sewer Tap Fees: Plant Investment Fees and Raw Water (2026)

Last reviewed: By Utility Cost Guide editor

Inside Greeley city limits, water and sewer service come from Greeley Water and Sewer, a city department that runs on customer and developer fees rather than taxes. A new single-family home on a standard lot (6,000 to 13,000 sq ft) with the usual 3/4-inch tap pays $26,400 in plant investment fees under the 2026 Rate Manual: a $16,900 water plant investment fee and a $9,500 sewer plant investment fee. The city’s storm drainage development fee adds $0.308 per square foot of roof, driveway and other hard surface. The caveat that moves the total most is raw water. Every lot has to bring water rights with it, three acre-feet per acre of land (a parcel over half an acre with one house is set at 1.5 acre-feet instead), and if the developer did not dedicate them the buyer pays cash in lieu at $57,000 per acre-foot, which is about $27,479 on a 7,000 sq ft lot.

Greeley tap and connection charges at a glance

The table below lists every Greeley row we recorded. Greeley does not charge single-family homes by tap size. It charges a share of the 3/4-inch tap value that depends on lot size and on whether the yard is watered with treated or non-potable water: 100% for standard and estate lots, 70% for medium lots of 4,500 to 5,999 sq ft, 60% for small lots and 50% for row houses and small-format lots. Only the 100% amount is printed as a dollar figure, so the smaller-lot rows are our arithmetic and are marked for review. The raw water row is a price per acre-foot, not a per-home amount, and is listed under other published fees because many subdivisions satisfy it with water rights at final plat. The meter charge row is from the city’s 2025 sheet.

ServiceCategoryFeeMeterAmountBasisEffectiveSourceVerified
General — Impact
GeneralImpactFire Development Fee - residential 1,801 sq ft or more of heated living space—$851per unit2026-03-01Official source2026-09-24
GeneralImpactPark Development Fee - residential 1,801 sq ft or more of heated living space—$6,316per unit2026-03-01Official source2026-09-24
GeneralImpactPolice Development Fee - residential 1,801 sq ft or more of heated living space—$327per unit2026-03-01Official source2026-09-24
GeneralImpactTrails Development Fee - residential 1,801 sq ft or more of heated living space—$947per unit2026-03-01Official source2026-09-24
GeneralImpactTransportation Development Fee - residential 1,801 sq ft or more of heated living space—$8,431per unit2026-03-01Official source2026-09-24
Sewer — Impact
SewerImpactSewer Plant Investment Fee - 3/4-inch tap3/4"$9,500by meter size—Official source2026-09-24
Stormwater — Impact
StormwaterImpactStorm Drainage Development Fee—$0.31per sq ft2026-03-01Official source2026-09-24
Water — Impact
WaterImpactCash-in-Lieu of Raw Water Dedication—$57,000formula—Official source2026-09-24
WaterImpactWater Plant Investment Fee - Estate Lot (over 13,000 sq ft), potable irrigation
Estate lot over 13,000 sq ft
3/4"$16,900formula—Official source2026-09-24
WaterImpactWater Plant Investment Fee - Medium Lot (4,500-5,999 sq ft), potable irrigation
Medium lot 4,500–5,999 sq ft
3/4"$11,830formula—Official source2026-09-24 Confirm with utility
WaterImpactWater Plant Investment Fee - Row House / Small Format (under 3,000 sq ft), potable irrigation
Row house or small format under 3,000 sq ft
3/4"$8,450formula—Official source2026-09-24 Confirm with utility
WaterImpactWater Plant Investment Fee - Small Lot (3,000-4,499 sq ft), potable irrigation
Small lot 3,000–4,499 sq ft
3/4"$10,140formula—Official source2026-09-24 Confirm with utility
WaterImpactWater Plant Investment Fee - Standard Lot (6,000-13,000 sq ft), potable irrigation
Standard lot 6,000–13,000 sq ft
3/4"$16,900formula—Official source2026-09-24
Water — Meter
WaterMeterMeter Charge - single-family3/4"$304by meter size—Official source2026-09-24 Confirm with utility

What a new Greeley house pays: worked example

The water plant investment fee comes from Greeley Municipal Code Sec. 20-262, which bases the residential fee on lot type, and the amounts in the 2026 Rate Manual from Greeley Water and Sewer. The sewer plant investment fee is the minimum set by the Water and Sewer Board under Sec. 20-325, and the city’s 2025 tap fee sheet says it is charged by the size of the domestic water tap. Raw water cash in lieu is three acre-feet per acre of lot times $57,000, which works out to about $3.93 per square foot of lot.

Assumptions: a detached home inside city limits, a 3/4-inch tap, the yard watered from the potable system, 3,500 sq ft of impervious surface for the storm drainage fee (our assumption; your site plan sets the real number), and a building permit pulled after March 1, 2026. Three lot sizes, each shown with and without the raw water payment:

Greeley connection charges by lot size, 2026 (Rate Manual and 2026 Development Impact Fee Schedule)

Charge 5,000 sq ft (medium lot) 7,000 sq ft (standard lot) 9,000 sq ft (standard lot)
Water plant investment fee $11,830 (70% × $16,900) $16,900 $16,900
Sewer plant investment fee $9,500 $9,500 $9,500
Storm drainage fee (3,500 sq ft × $0.308) $1,078 $1,078 $1,078
Subtotal, water rights already dedicated $22,408 $27,478 $27,478
Raw water required (lot acres × 3) 0.344 acre-foot 0.482 acre-foot 0.620 acre-foot
Cash in lieu at $57,000 per acre-foot $19,628 $27,479 $35,331
Total, raw water paid in cash $42,036 $54,957 $62,809

For the 7,000 sq ft lot, the arithmetic is $16,900 + $9,500 + $1,078 = $27,478, and 7,000 ÷ 43,560 × 3 = 0.482 acre-foot × $57,000 = $27,479 for the water. On a standard lot, water rights are half of the cash total. Two details change the water fee. A lot watered from a shared non-potable system pays 75% of the tap value on a standard lot, or $12,675, and a lot on house-to-house non-potable irrigation pays 50%, or $8,450. The 2025 tap fee sheet also listed a $304 meter charge for a single-family home; we found no 2026 amount, and the city describes meters as a pass-through of its purchase cost.

The 70%, 60% and 50% amounts for smaller lots are our multiplication of the percentages printed in the Rate Manual, and we applied the lot-size percentages to the water fee only. The manual applies them to “the applicable tap size-based values,” a table that lists both the water and the sewer fee, but it prints no sewer amounts by lot type. If the percentage also covers sewer, the 5,000 sq ft lot’s sewer fee would be $6,650 (70% × $9,500) rather than $9,500. Confirm both with Greeley Water and Sewer (970-350-9811) before you budget a small-lot home.

How Greeley compares with Fort Collins and Erie

All three cities charge a capacity fee and require water rights, but they price them differently. The Fort Collins page shows $8,354 in plant investment fees for a 6,000 sq ft lot, with water rights at $63,800 per acre-foot on top. Greeley’s $26,400 in plant investment fees on a standard lot is $18,046 more than that Fort Collins example, although Greeley’s cash price per acre-foot is $6,800 lower. The Erie page puts a 3/4-inch tap at $28,012 without water rights and $80,212 with Erie’s $52,200 fee in lieu of water dedication. Greeley’s 7,000 sq ft example is close to Erie before water ($27,478 against $28,012) and $25,255 lower with water paid in cash ($54,957 against $80,212).

What is not included in Greeley fees

Greeley’s website says the connection from the curb stop or the sewer main to the building is the owner’s responsibility, and the code makes the applicant pay for the meter, labor and materials to make the tap. The plant investment fees do not cover that work, the plumbing permit or the city’s police, fire, park, trails and transportation impact fees. The largest-home tier of those five (1,801 sq ft or more of heated space) adds up to $16,872 in 2026. These private-side figures are national estimates, not Greeley prices (methodology), and the per-foot numbers already include trenching:

We did not collect electric or gas charges for Greeley; line extension costs are quoted per project by the serving utility. Enter your lot and line lengths in the calculator:

Estimate utility connection costs

Estimates are planning figures, not quotes. Confirm fees and trench rules with your utility.

Location and property
Services and site work

Many codes require horizontal separation between water and sewer. This estimate assumes separate water and sewer trenches unless you select a shared run where your utility allows it.

Quoted fees and comparison assumptions

Paying Greeley fees: timing and process

Water rights dedicated as shares are due at final plat, and Greeley accepts only certain sources: Greeley-Loveland system shares, Colorado-Big Thompson units, Terry Ranch credits, and Greeley Irrigation Company shares for non-potable use. The city’s raw water page says cash in lieu and Terry Ranch credits must accompany the building permit. Plant investment fees and tap installation costs are paid no later than building permit issuance under Secs. 20-263 and 20-265. After payment, the city drills the tap and sets the meter. The storm drainage and other city impact fees are also collected with the building permit.

What could change in Greeley

Common questions about Greeley fees

How much is a water and sewer tap in Greeley, CO?

For a single-family home on a standard lot of 6,000 to 13,000 sq ft, the 2026 plant investment fees are $16,900 for water and $9,500 for sewer, or $26,400. Smaller lots pay 50% to 70% of the water amount. Raw water, the storm drainage fee and the meter are extra.

What is Greeley’s cash-in-lieu of raw water fee?

It is $57,000 per acre-foot in the 2026 Rate Manual. Single-family development must supply three acre-feet per acre of land, so a 7,000 sq ft lot needs 0.482 acre-foot, about $27,479 in cash, unless water rights were dedicated for the lot at plat.

Do I pay raw water fees if my builder’s subdivision already dedicated water?

No cash is due for the portion already covered. The city says no cash in lieu is owed when enough acceptable raw water was dedicated or when existing taps on the property carry enough credit. Ask the builder or Greeley Water and Sewer to confirm before permit.

Why does lot size change the Greeley water fee?

Row houses and small-format lots pay 50% of the $16,900 tap value, small lots 60%, medium lots 70%, and standard and estate lots 100%.

When are Greeley tap fees paid?

Plant investment fees, tap costs and cash in lieu are due by building permit issuance. Water shares dedicated instead of cash are due at final plat.