Erie Water and Sewer Tap Fees and Raw Water Fees (2026)

Last reviewed: By Utility Cost Guide editor

In the Town of Erie, the town itself provides water, wastewater and storm drainage service, and a new single-family home pays four utility charges before it can connect. For a home with the standard 3/4-inch tap on a lot of 7,000 sq ft or less, the 2026 total is $80,212: a $17,290 potable water tap fee, a $52,200 fee in lieu of water dedication, an $8,860 wastewater tap fee and a $1,862 storm drainage impact fee. The first three come from the town’s 2026 fee schedule, adopted by Resolution 26-104, and the storm fee from the town’s fee schedules page. The biggest caveat is water supply. The $52,200 is not a connection charge: it is the fee in lieu of water dedication, which pays for the water rights needed to serve the home, and it has been $52,200 since May 26, 2026 (it was $31,400 in 2025). A developer can dedicate water rights the town accepts instead of paying it, which leaves $28,012 in utility charges. Since May 2026 the town has also limited how many new water allocations it hands out.

Erie tap and connection charges at a glance

The table lists every Erie row we verified. Water and wastewater tap fees are priced by water tap size. The fee in lieu of water dedication, which Erie also calls the raw water fee or potable water rights fee, is a separate charge from the water tap fee. The schedule prints an amount only for the 3/4-inch residential tap. Larger taps and non-residential uses are priced from a water-demand analysis. Rows marked as not typical cover small homes, the fire sprinkler surcharge, the non-potable irrigation tap and the town’s impact fees for parks, police, public buildings, roads and trees, which are not utility charges.

ServiceCategoryFeeMeterAmountBasisEffectiveSourceVerified
General — Impact
GeneralImpactParks and Recreation Impact Fee - single-family detached—$2,803per unit—Official source2026-09-24
GeneralImpactPolice Facilities Impact Fee - single-family detached—$686per unit—Official source2026-09-24
GeneralImpactPublic Facilities Impact Fee - single-family detached—$4,276per unit—Official source2026-09-24
GeneralImpactTransportation Facilities Impact Fee (outside Town Center and Historic Old Town) - single-family detached—$6,402per unit—Official source2026-09-24
GeneralImpactTransportation Facilities Impact Fee (Town Center PD and Historic Old Town OTR/NMU/DT/MR zones) - single-family detached—$4,546per unit—Official source2026-09-24
GeneralImpactTree Impact Fee - single-family detached—$300per unit—Official source2026-09-24
Reclaimed — Tap
ReclaimedTapNon-potable Water Tap Fee—$17,410varies—Official source2026-09-24
Sewer — Tap
SewerTapWastewater Tap Fee - 1 inch1"$14,767by meter size—Official source2026-09-24
SewerTapWastewater Tap Fee - 3/4 inch3/4"$8,860by meter size—Official source2026-09-24
Stormwater — Impact
StormwaterImpactStorm Drainage Impact Fee - single-family detached—$1,862per unit—Official source2026-09-24
Water — Capacity
WaterCapacityFee in Lieu of Water Dedication (Potable Water Rights Fee / Raw Water Fee) - 3/4 inch3/4"$52,200by meter size2026-05-26Official source2026-09-24
Water — Other
WaterOtherFireflow Surcharge (3/4-inch tap with automatic sprinkler system)3/4"$170flat fee—Official source2026-09-24
Water — Tap
WaterTapPotable Water Tap Fee - Small home—$12,967.50per unit—Official source2026-09-24
WaterTapPotable Water Tap Fee - 1 inch1"$28,820by meter size—Official source2026-09-24
WaterTapPotable Water Tap Fee - 3/4 inch3/4"$17,290by meter size—Official source2026-09-24

What each charge pays for

The town’s rates and charges page separates the three water charges. Water tap fees buy a share of the treatment plants, transmission lines, pump stations and storage tanks, and the fee schedules page adds that they cover the physical tap and the meter. Water dedication fees pay for water rights, both supplies Erie already owns and new supplies still to be acquired; the town names NISP, Boulder Creek Supply and Windy Gap Firming among its sources. The wastewater tap fee does the same job for sewer.

Town of Erie water and wastewater tap fees by tap size, 2026 (Resolution 26-104)

Tap size Potable water tap fee Fee in lieu of water dedication Wastewater tap fee
Small home $12,967.50 not listed not listed
3/4 inch $17,290 $52,200 $8,860
1 inch $28,820 by demand analysis $14,767
1.5 inches $57,630 by demand analysis $29,533
2 inches $92,210 by demand analysis $47,253

A small home is a dwelling under 1,000 sq ft on a lot of 2,000 sq ft or less. The schedule allows $1,729 to be added to its $12,967.50 water tap fee for each additional 1,000 sq ft of lot. Erie’s water dedication guide sets the water rights requirement in single-family equivalents (SFE). A standard single-family lot of 7,000 sq ft or less needs 1.0 SFE: 0.5 SFE for indoor use and the rest for outdoor watering. A larger lot needs 1.0 SFE or more, based on its irrigable area, so its fee in lieu can be higher than $52,200. The guide does not print that larger amount.

Worked example: a new home in Erie

Assumptions: a detached home inside town limits, a 3/4-inch water tap, a lot of 7,000 sq ft or less, a building permit applied for on or after May 26, 2026, and a developer who has not dedicated water rights for the lot.

Town of Erie connection charges for one single-family home, 3/4-inch tap, 2026

Charge Water fee paid in cash Water rights dedicated by developer Cash, home with fire sprinklers
Potable water tap fee $17,290 $17,290 $17,290
Fireflow surcharge $0 $0 $170
Fee in lieu of water dedication $52,200 $0 $52,200
Wastewater tap fee $8,860 $8,860 $8,860
Storm drainage impact fee $1,862 $1,862 $1,862
Total $80,212 $28,012 $80,382

The arithmetic for the first column is $17,290 + $52,200 + $8,860 + $1,862 = $80,212. The water rights fee is 65% of it. The middle column assumes the subdivision already dedicated water rights for the lot; ask the builder or the town which applies. The $170 fireflow surcharge applies only when a home with a 3/4-inch tap also needs an automatic fire sprinkler system. A 1-inch tap adds $11,530 to the water tap fee and $5,907 to the wastewater fee. A lot outside town limits needs Town Council approval for service, and the fees above are doubled.

Erie’s town impact fees are separate from the utility charges. A single-family detached home pays $2,803 for parks and recreation, $686 for police, $4,276 for public facilities, $300 for trees and $6,402 for transportation, or $14,467 in all. In the Town Center planned development and the Historic Old Town zones the transportation fee is $4,546, for a total of $12,611. The school district also requires a land dedication or a cash-in-lieu fee, paid before the building permit issues.

How Erie compares with Denver, Aurora and Castle Rock

Erie’s cash total is higher than Denver, Aurora and Castle Rock, and water rights explain the gap. On the Denver page, Denver Water’s system development charge for an 8,000 sq ft lot is $11,460 from July 1, 2026, and the city sewer permit is $6,480, for $17,940. Aurora Water’s own example of a 3-bath home on an 8,000 sq ft lot comes to $44,456. Castle Rock Water charges $46,336.84 for a 3,500–3,999 sq ft home in the Plum Creek Basin. Erie’s $80,212 is $62,272 more than the Denver example $35,756 more than Aurora and $33,875.16 more than Castle Rock. Erie’s water rights fee alone ($52,200) is larger than Aurora’s or Castle Rock’s whole bill. Without it, Erie’s $28,012 sits between Denver and the other two suburbs.

What Erie’s fees don’t cover

The tap fees pay for the connection and for system and water supply capacity. They do not pay for the pipes on your lot. A contractor builds the water service line to the house and the sewer service line to the main, and trenching, any street cut, and the building and plumbing permits are extra. Erie’s building and plumbing permit fees depend on project valuation, so we don’t list a fixed amount. These planning figures are national estimates, not Erie prices (how we built them), and the per-foot figures already include trenching:

We have not collected electric or gas charges for Erie. Electric line extension costs depend on the utility serving the lot and are quoted per project. Enter your tap size and line lengths in the calculator:

Estimate utility connection costs

Estimates are planning figures, not quotes. Confirm fees and trench rules with your utility.

Location and property
Services and site work

Many codes require horizontal separation between water and sewer. This estimate assumes separate water and sewer trenches unless you select a shared run where your utility allows it.

Quoted fees and comparison assumptions

How and when Erie fees are paid

The fee schedule says the fee in lieu of water dedication may be paid when you apply for a building permit, which secures a water allocation from the town’s supply, and it must be paid in full before the permit is issued. Ordinance 039-2024 says water tap fees and the fee in lieu are paid at the time of the water service application, as set in the fee schedule. The water dedication guide says Erie will not provide water taps or service until the water dedication requirement is met, either by transferring water rights the town accepts or by paying the fee in lieu. Once the house is occupied, the town bills a monthly storm drainage fee of $13.72 per single-family equivalent in 2026, plus water and sewer charges.

Erie fee changes to watch

Erie tap fee FAQ

How much are water and sewer tap fees in Erie, CO?

For a new single-family home with a 3/4-inch tap in 2026, the potable water tap fee is $17,290 and the wastewater tap fee is $8,860, or $26,150 together. Unless water rights were already dedicated for the lot, the home also owes a $52,200 fee in lieu of water dedication and a $1,862 storm drainage impact fee, which brings the total to $80,212.

What is Erie’s raw water fee?

It is the fee in lieu of water dedication, also called the potable water rights fee. It pays for the water rights needed to serve the home. In 2026 it is $52,200 for a 3/4-inch residential tap on a lot of 7,000 sq ft or less. It is separate from the water tap fee.

Can I avoid the $52,200 water dedication fee?

Only by meeting the requirement another way. The town accepts dedication of water rights it has evaluated, and it says developers often buy Colorado-Big Thompson shares, which can cost two to three times its fee. If your subdivision’s developer already dedicated water for your lot, ask the town to confirm before you pay.

Is Erie more expensive than Denver or Aurora for a new home?

Yes. Erie’s $80,212 for a 3/4-inch tap compares with $17,940 for Denver’s 8,000 sq ft lot example and $44,456 for Aurora’s 3-bath example. Without the water rights fee, Erie’s charges are $28,012.

Why is Erie limiting new water allocations?

Delays in the Chimney Hollow and NISP projects pushed back water the town expected to use. Under the May 2026 policy, Erie divides its remaining supply among public projects, economic development, residential development, affordable housing and contingency. Council confirms the allocations each year.

Related guides for Erie

Colorado utility connection costs · Denver Water tap fees · Aurora Water tap fees · Castle Rock Water system development fees · Fort Collins plant investment fees · tap fee vs impact fee · utility connection cost calculator