Frisco Water & Sewer Tap and Impact Fees (2026)

Last reviewed: By Utility Cost Guide research team

The City of Frisco provides water and wastewater through its Public Works department, and a new single-family home pays a meter fee plus water and wastewater impact fees. The published figures add up to about $5,299: an $835 residential meter fee for a 1-inch meter (effective March 2, 2026, including a $150 deposit) and $4,464 in impact fees ($2,120 water plus $2,344 wastewater per service unit). The main caveat is that the impact-fee table the city links is from 2019 and we could not find a newer one, so confirm those two numbers before you budget. Tap fees are not published at all; Public Works quotes them per tap.

Official fees at a glance

Frisco publishes limited connection detail, and the table below shows everything we could verify. The meter fee comes from the city’s current fee schedule and is verified. The two impact-fee rows come from the city’s Water and Wastewater Impact Fee Table, which dates from a 2019 ordinance; they are marked for review for that reason. The smallest residential meter in Frisco’s fee table is 1 inch, so there is no 5/8-inch or 3/4-inch option to price.

ServiceCategoryFeeMeterAmountBasisEffectiveSourceVerified
Sewer — Impact
SewerImpactWastewater Impact Fee per Service Unit - Single Family (1" PD)1"$2,344by meter sizeOfficial source2026-09-24 Needs review
Water — Impact
WaterImpactWater Impact Fee per Service Unit - Single Family (1" PD)1"$2,120by meter sizeOfficial source2026-09-24 Needs review
Water — Meter
WaterMeterResidential Utility Meter Fee - 1-inch T-101"$835by meter size2026-03-02Official source2026-09-24

Worked example: a new single-family home

Assumptions: detached house, one 1-inch T-10 meter, one service unit, meter site ready on the first visit. Meter fee from the Frisco fee schedule; impact fees from the Water and Wastewater Impact Fee Table (2019, needs review).

Published City of Frisco charges for one single-family home, 1-inch meter.

Line item Case A: taps already in place Case B: meter site not ready at first visit
Residential meter fee, 1″ T-10 (incl. $150 deposit) $835 $835
Water impact fee, single family $2,120 $2,120
Wastewater impact fee, single family $2,344 $2,344
Not-ready charge $100
Total $5,299 $5,399

Of the $835 meter fee, $150 is a deposit, so the non-refundable part is $685 and the non-refundable total in Case A is $5,149.

The impact-fee table also shows how Frisco sets its single-family rate. Other land uses pay $3,028 for water and $3,348 for wastewater per service unit; single-family homes are charged 70 percent of the maximum. The arithmetic checks out: $3,028 × 0.70 = $2,119.60, published as $2,120, and $3,348 × 0.70 = $2,343.60, published as $2,344. A single-family home therefore pays $1,912 less than the full rate would be ($6,376 − $4,464).

If the lot needs a new tap at the main, add the Public Works quote. Frisco does not publish a figure, so the only numbers we can offer are national estimates: $500–$5,500 for a residential water tap or connection fee (typically about $1,600) and $200–$6,100 for a sewer tap (typically about $3,000). With typical national figures, Case A would become $5,299 + $1,600 + $3,000 = $9,899. Treat that as a planning placeholder, not a Frisco price.

What these fees don’t include

National figures are estimates from our benchmark set. The calculator combines Frisco’s published fees with your line lengths:

Estimate utility connection costs

Estimates are planning figures, not quotes. Confirm fees and trench rules with your utility.

Location and property
Services and site work

Many codes require horizontal separation between water and sewer. This estimate assumes separate water and sewer trenches unless you select a shared run where your utility allows it.

Quoted fees and comparison assumptions

How and when you pay

Frisco sets meters itself. According to the city’s Meter Sets and Payment guidance, meters smaller than 2 inches are usually set the next business day after payment. If crews arrive and the meter site is not ready, the city charges $100. Tap work is priced separately by Public Works, so ask for the quote early if your lot does not already have a service stub.

The impact fees on this page come from a 2019 table that is still the latest one the city links. Frisco may have updated it since without a document we could find. Ask the city to confirm the current single-family rate for your plat before closing or pricing a build.

Changes to watch

Frisco tap fee FAQ

How much are Frisco’s water and sewer impact fees?

The city’s impact fee table lists $2,120 for water and $2,344 for wastewater per service unit for single-family homes, $4,464 combined. That table dates from 2019, so confirm it is still current.

What does the Frisco meter fee cost?

A 1-inch T-10 residential meter is $835, including a $150 deposit, effective March 2, 2026. A 2-inch meter is $1,425.

Why is Frisco’s smallest meter 1 inch?

Frisco’s residential meter table starts at 1 inch; it does not list 5/8-inch or 3/4-inch residential meters. Every new house is priced from the 1-inch line.

How long does it take Frisco to set a meter?

Meters under 2 inches are usually set the next business day. If the site is not ready when crews arrive, the city charges $100.

How much is a tap fee in Frisco?

Frisco does not publish a tap fee; Public Works quotes each tap. National estimates put residential water taps at $500 to $5,500 and sewer taps at $200 to $6,100, but ask the city for your lot.