Dallas Water Utilities Tap & Connection Fees (2026)
Dallas Water Utilities provides water and wastewater inside the City of Dallas, and permits for new service run through the city’s Planning & Development Department. For a new single-family home, the official city charges are small: $465.50 to inspect the water service plus $465.50 to inspect the 6-inch sewer lateral, $931 in total under the fee schedule effective October 1, 2025. The catch is what that number leaves out. Since October 1, 2024, Dallas Water Utilities no longer installs residential taps, so every owner hires a registered, bonded contractor to build the water tap, service line and sewer lateral, and the city does not publish that contractor price.
Dallas connection fees at a glance
The table below lists every Dallas row in our database with its source. The two inspection fees come from the Planning & Development Meter and Wastewater Fee Schedule (effective October 1, 2025); City Code Section 49-18.7 sets the same $465.50 inspection fee for larger and commercial connections built by the applicant. The lot fees and the account deposit come from Dallas City Code Chapter 49 (Sections 49-18.10 and 49-18.8). The lot fees are conditional: they apply only on a first connection to a main that a developer built with city cost participation, so many lots never see them. The deposit is refundable and belongs to the water account, not to construction.
| Service | Category | Fee | Meter | Amount | Basis | Effective | Source | Verified |
|---|---|---|---|---|---|---|---|---|
| Sewer — Connection | ||||||||
| Sewer | Connection | 6" Lateral - Lateral Connection Fee (new connection by DWU to DWU lateral, tap in place) Existing lateral; new connection | — | $475 | flat fee | 2020-10-01 | Official source | 2026-09-24 Confirm with utility |
| Sewer — Inspection | ||||||||
| Sewer | Inspection | 6" Lateral - inspection only (bonded contractor) | — | $275 | flat fee | 2020-10-01 | Official source | 2026-09-24 Confirm with utility |
| Sewer | Inspection | 6" wastewater lateral connection inspection (bonded contractor) | — | $465.50 | flat fee | 2025-10-01 | Official source | 2026-09-24 |
| Sewer — Main Extension | ||||||||
| Sewer | Main Extension | Lot fee for individual owners - subdivided lot using an existing wastewater main | — | $0.02 | per sq ft | — | Official source | 2026-09-24 |
| Sewer — Tap | ||||||||
| Sewer | Tap | 6" Lateral - Lateral Conversion Fee, installation and inspection (City Contractor) City installs lateral | — | $4,060 | flat fee | 2020-10-01 | Official source | 2026-09-24 Confirm with utility |
| Water — Connection | ||||||||
| Water | Connection | Dead Head Conversion Fee - service line with 3/4" deadhead Existing stubbed deadhead service | 3/4" | $890 | by meter size | 2020-10-01 | Official source | 2026-09-24 Confirm with utility |
| Water — Deposit | ||||||||
| Water | Deposit | Standard security deposit, residential service account (5/8" and 3/4" meter) | 3/4" | $100 | by meter size | — | Official source | 2026-09-24 |
| Water — Inspection | ||||||||
| Water | Inspection | Inspection fee per tap (bonded contractor installation) | — | $275 | flat fee | 2020-10-01 | Official source | 2026-09-24 Confirm with utility |
| Water | Inspection | Water service inspection, 2" or smaller (bonded contractor installation) | — | $465.50 | flat fee | 2025-10-01 | Official source | 2026-09-24 |
| Water — Main Extension | ||||||||
| Water | Main Extension | Lot fee for individual owners - subdivided lot using an existing water main | — | $0.02 | per sq ft | — | Official source | 2026-09-24 |
| Water — Tap | ||||||||
| Water | Tap | Water connection requiring tap to main - 1" service line with 1" service (City Contractor) | 1" | $4,200 | by meter size | 2020-10-01 | Official source | 2026-09-24 Confirm with utility |
| Water | Tap | Water connection requiring tap to main - 3/4" service line with 3/4" service (City Contractor) New tap to main | 3/4" | $3,790 | by meter size | 2020-10-01 | Official source | 2026-09-24 Confirm with utility |
Worked example: a new home in Dallas
Assume a new house on a subdivided lot with a 3/4-inch or 1-inch water service and a 6-inch sewer lateral, both installed by your bonded contractor. The inspection fee is the same $465.50 for 3/4-inch, 1-inch, 1-1/2-inch and 2-inch services, per the Meter and Wastewater Fee Schedule (effective Oct 1, 2025). The lot fee is $0.018 per square foot for water and another $0.018 per square foot for wastewater under Dallas City Code Sec. 49-18.10.
Official City of Dallas charges for one new single-family home, three lot cases (contractor construction not included).
| Case | Water inspection | Sewer lateral inspection | Lot fees (water + sewer) | Official total |
|---|---|---|---|---|
| No lot fee owed | $465.50 | $465.50 | — | $931.00 |
| 7,500 sq ft lot, lot fee owed | $465.50 | $465.50 | 7,500 × $0.018 × 2 = $270.00 | $1,201.00 |
| 10,000 sq ft lot, lot fee owed | $465.50 | $465.50 | 10,000 × $0.018 × 2 = $360.00 | $1,291.00 |
When the account is opened, a residential customer with a 5/8-inch or 3/4-inch meter also posts a $100 security deposit ($125 for a 1-inch meter) under City Code Sec. 49-18.8. We leave it out of the totals because it is refundable.
An unsubdivided tract pays the lot fee by the acre instead: $785 per acre for an existing water main and $785 per acre for an existing wastewater main. A one-acre tract that owes both would add $1,570 rather than the per-square-foot amounts above.
Two things we could not put a number on. First, the installation application says the bonded contractor requests the meter from Dallas Water Utilities’ Distribution Division, but neither it nor the fee schedule prints a separate charge for a small residential meter, so ask when you apply. Second, we did not find a water or wastewater impact fee in the Dallas fee documents we read, which is unusual among large Texas cities. Confirm that with Planning & Development before you rely on it.
Costs outside the Dallas fee schedule
In Dallas the construction work is now the owner’s cost, and it is by far the largest piece:
- The tap, water service line and sewer lateral in the public right-of-way, built by your bonded contractor. The city publishes no price for this. For a sense of scale, the last city-contractor prices Dallas published, in its permit fee table effective October 1, 2023, were $6,190 for a new 3/4-inch water service and $6,890 for a 6-inch wastewater lateral. Those prices were discontinued, so treat them as history, not a quote.
- Water service line from the meter to the house. National estimate $30–$150 per foot, typically about $50. See water service line cost.
- Sewer lateral on private property. National estimate $50–$250 per foot, typically about $100. See sewer lateral cost.
- Hard digging and pavement repair. The per-foot estimates above already include trenching in normal soil; national estimates put trenching in clay or rock at 1.2× to 7× the normal-soil cost. See utility trenching cost.
- Building and plumbing permits, which Dallas lists separately from these water and wastewater charges.
National figures are estimates from our benchmark set. Enter your contractor’s quote in the calculator to see the full picture with Dallas’s official fees loaded:
Estimate utility connection costs
Estimates are planning figures, not quotes. Confirm fees and trench rules with your utility.
How and when Dallas fees are paid
You apply with the city’s Water and Wastewater Service Installation Application. For a new single-family home or duplex, the completed application is uploaded with the building permit in ProjectDox; for an addition or remodel, it is emailed to BIWaterWastewater@dallas.gov after the building permit is issued. Every submission needs a signed agreement from a registered, bonded contractor. The permit cannot be transferred and expires one year after issue.
The application states that Dallas Water Utilities discontinued city-contractor installation on October 1, 2024, and that the $465.50 inspection fee applies to each installation. Your contractor calls Dallas Water Utilities’ Distribution Division to request the meter. Water Distribution must inspect the work before the permit can close. Wastewater Collections must inspect before the contractor connects to the city lateral or main; Building Inspection makes that referral and no appointment is needed.
If a lot fee applies, City Code Sec. 49-56(h) says it is charged at the rate in effect on the day you apply for the service connection permit and must be paid before the permit is issued.
Upcoming changes in Dallas
- Annual fee ordinance. Dallas adjusts water and wastewater charges in its fiscal-year fee ordinance, which takes effect with the October 1 fiscal year. The FY2025-26 ordinance, approved as amended on September 17, 2025, raised the connection inspection fee from $275 to $465.50 and removed the city’s residential installation price tables from Section 49-18.7. Check for an FY2026-27 change after October 1, 2026.
- Meter charges. The published schedule gives meter and hatch prices only for services larger than 2 inches. Ask Dallas Water Utilities what, if anything, it charges for a 3/4-inch or 1-inch residential meter.
- Lot and acreage fees. The $0.018 per square foot and $785 per acre rates in Sec. 49-18.10 were not changed by the FY2025-26 ordinance.
Dallas tap fee FAQ
How much does Dallas charge to connect a new house to water and sewer?
The city’s own charges are $465.50 to inspect the water service and $465.50 to inspect the sewer lateral, $931 in total under the schedule effective October 1, 2025. A lot fee of $0.018 per square foot per service can apply on some lots. The contractor’s construction cost is separate and not published.
Does the City of Dallas still install water taps?
No. Dallas Water Utilities stopped city-contractor installation on October 1, 2024. You must hire a registered, bonded contractor, and the city inspects the work for $465.50 per installation.
What was the old Dallas price for a 3/4-inch water tap?
The city’s table effective October 1, 2023 listed $6,190 for a new 3/4-inch water service and $6,890 for a 6-inch sewer lateral. Those were city-contractor prices and are no longer offered.
Who pays the Dallas lot fee?
An owner connecting for the first time to an existing main that a developer built with city participation. It is $0.018 per square foot of a subdivided lot for water and the same for wastewater, or $785 per acre for unsubdivided land, paid before the connection permit is issued.
How much is the Dallas water deposit?
A residential account posts a $100 security deposit for a 5/8-inch or 3/4-inch meter, $125 for 1-inch, $150 for 1-1/2-inch and $200 for 2-inch and larger, under City Code Sec. 49-18.8.
Does Dallas charge water or wastewater impact fees?
We did not find one in the Dallas fee schedule or Chapter 49 sections we read, unlike Fort Worth or Houston. Ask Planning & Development to confirm for your address, especially if the lot is served by a neighboring utility or district.
North of the Red River, Oklahoma City water and sewer connection fees are set by the number of baths.
Related: Texas utility connection costs by city · Fort Worth fees · Frisco fees · McKinney fees · Houston fees · water tap fees · sewer tap fees · tap fee vs. impact fee · utility connection cost calculator
Sources for Dallas figures
- Meter and Wastewater Fee Schedule (effective October 1, 2025), City of Dallas Planning & Development (checked Sep 24, 2026)
- Water and Wastewater Service Installation Application (26-001), City of Dallas Planning & Development (checked Sep 24, 2026)
- Dallas City Code Chapter 49, Sections 49-18.7, 49-18.8 and 49-18.10, City of Dallas via American Legal Publishing, Code S-33 (checked Sep 24, 2026)
- Dallas City Code Sec. 49-56 (lot and acreage fees), City of Dallas via American Legal Publishing (checked Sep 24, 2026)
- New Permit Fees, effective October 1, 2023 (discontinued city-contractor prices), City of Dallas (checked Sep 24, 2026)
- FY2025-26 fee ordinance, File 25-2339A (approved as amended Sep 17, 2025), City of Dallas (checked Sep 24, 2026)