How Many Feet of Power Line Will the Utility Run for Free?

Published By Utility Cost Guide editor

It depends entirely on your utility’s line extension tariff, and the range is wide. Pioneer Electric Cooperative in Kansas builds the first quarter mile (1,320 feet) of single-phase line at no charge. Kentucky’s utility regulation requires 1,000 free feet for a single-phase customer. Oncor in Texas builds 300 feet of overhead line free for a typical home, while NorthWestern Energy in South Dakota builds 500. Others don’t count feet at all. Arizona Public Service gives a $10,000 credit per home. Cherryland Electric Cooperative in Michigan charges $6.00 per foot from the first foot, and Versant Power in Maine bills the full cost.

This article covers the allowance rules themselves. For total budgets at 200, 500 and 1,000 feet, poles and meter bases, see cost to run power to a property. For who pays for the transformer, see who pays for a new home’s transformer.

Free footage and allowances, utility by utility

Residential, single-phase, permanent service. Figures as printed in each tariff or rule; wording paraphrased. Documents checked September 24, 2026.

Utility (type, state) Allowance type What you get free Beyond the allowance Refund if others connect Source
Pioneer Electric Cooperative (co-op, KS) Footage First 1,320 ft of single-phase line $6.50/ft overhead primary, $10.00/ft underground primary; three-phase priced at $9.50/ft from the first foot None stated Line extension cost page, checked Sept. 24, 2026
Utilities regulated by the Kentucky PSC Footage (state rule) 1,000 ft of single-phase line where transformer capacity is 25 kVA or less; the service drop is not counted Deposit for the excess feet at the average estimated cost per foot Yes, for at least 10 years 807 KAR 5:041, Sec. 11
NorthWestern Energy (investor-owned, SD) Footage 0–500 ft overhead or underground, shortest feasible route Over 500 ft, a contribution may be required after an economic study None stated Tariff Sec. 6, sheet 9.1 (service agreement form), eff. Mar. 1, 2024
Oncor (wires company, TX) Footage 300 ft of overhead single-phase line, including the drop, for loads under 20 kW; underground free if it costs no more than 300 ft of overhead Non-refundable contribution at an estimated cost per foot (overhead) or a cost study (underground) No Sec. 6.1.2.2.5, tariff eff. June 1, 2026
Arizona Public Service (investor-owned, AZ) Dollar cap Up to $10,000 of primary, secondary and service per home, not counting one single-phase transformer Everything over $10,000, as a non-refundable contribution No, for a single home Service Schedule 3, eff. Mar. 8, 2024
Xcel Energy / Public Service Co. of Colorado (investor-owned) Percentage credit plus dollar allowance 35% credit on the line extension to your property; $150 toward the service lateral 65% of the off-site line cost; lateral $517 for the first 100 ft, then $5.87/ft No (payments non-refundable) Colo. PUC No. 8, sheets R200–R229, Advice Letter 1800, eff. Oct. 1, 2019 (sheet R227 rev. July 23, 2021)
Holy Cross Energy (co-op, CO) Dollar allowance $1,000 per qualifying line extension Remaining line extension cost Yes, from new members who tap the line within 10 years Rule 3030, eff. Apr. 1, 2026
Liberty Utilities CalPeco (investor-owned, CA) Revenue-based $2,923 per residential meter under a Dec. 2024 filing; formula ties it to the average bill Refundable advance Yes, over 10 years Advice Letter 223-E, Rule 15
Cherryland Electric Cooperative (co-op, MI) Flat per-foot price, no free footage None; $100 connection charge $6.00/ft for the first year-round home on a parcel; runs over 800 ft reviewed case by case No (non-refundable) Rate Book No. 5, sheets C-14 to C-16, eff. Jan. 1, 2024
Claiborne Electric Cooperative (co-op, LA) Investment-based A construction allowance equal to year-end net utility plant divided by active meters, recalculated each year Contribution; homeowners may pay over up to 60 months at prime plus 5% Developers only, up to 60 months LPSC Tariff No. 1, eff. Mar. 7, 2024
Versant Power (investor-owned, ME) No allowance None Full line extension cost per foot, plus tree trimming, ledge and tax charges Later customers on the line pay a share under Maine’s Chapter 395 Terms and Conditions, Sec. 5, eff. Aug. 31, 2022

Allowances assume a permanent home with an ordinary single-phase load: Kentucky’s rule stops at 25 kVA of transformer capacity, Oncor’s at 20 kW of demand. A barn, RV pad or three-phase shop usually falls under a less generous rule.

Three ways utilities measure “free”

Footage

Footage is the easiest allowance to check yourself, but read the measurement rule first. Oncor counts primary, secondary and the service drop together, along the route the company chooses. Kentucky’s rule leaves the drop out, and NorthWestern measures along the shortest feasible route. Holy Cross says the route’s origin need not be the nearest point on its system, so a tape-measure estimate can come up short.

Footage allowances also stack. Oncor gives two applicants who sign up before construction 600 free feet, and APS lets a group combine its $10,000 caps. If neighbors are building too, apply together.

Dollar allowances and credits

A dollar allowance comes off the utility’s cost estimate, so it is worth more on cheap overhead construction than on underground work or rock. Holy Cross applies $1,000. APS covers up to $10,000. Xcel Colorado now uses a percentage: it takes 35% off the construction cost of a line extension to reach your property, and gives a $150 allowance on the service lateral. On Xcel’s standard lateral cost of $517 for the first 100 feet, you pay $517 − $150 = $367. At 250 feet you pay $367 + (150 × $5.87) = $1,247.50.

Revenue- or investment-based allowances

Some utilities tie the allowance to what they expect to earn from you, or to their average investment per customer. Liberty’s December 2024 filing shows the math: an average annual residential bill of $2,261.62 divided by a cost-of-service factor of about 0.7739 (the filing’s expenses divided by its revenue) gives $2,922.53, rounded to a $2,923 allowance per meter. The filing asked for a January 1, 2025 effective date; the older Rule 15 sheet on Liberty’s site describes the allowance as 2.5 times annual revenue. Claiborne Electric divides its net plant by its number of meters each year and does not print the result, so ask for the current figure.

Look for the word “non-refundable” in the tariff. Oncor, APS, Xcel Colorado’s current policy and Cherryland treat what you pay as a contribution you never get back. Kentucky, Holy Cross and Liberty treat part of it as an advance that later customers can pay down.

Worked examples

Line extension charge only, using each tariff’s published numbers. Excludes the meter base, panel, permit and any transformer charge.

Utility 800 ft overhead, single-phase 1,800 ft overhead, single-phase
Pioneer Electric Cooperative $0 (inside 1,320 ft) 480 billable ft × $6.50 = $3,120
Kentucky PSC rule $0 (inside 1,000 ft) Deposit for 800 ft at the utility’s average cost per foot
NorthWestern Energy SD 300 ft over the free 500; charge set by economic study 1,300 ft over; charge set by economic study
Oncor 500 ft over the free 300, at estimated cost per foot 1,500 ft over, at estimated cost per foot
Cherryland Electric Cooperative 800 × $6.00 + $100 = $4,900 Over 800 ft: reviewed case by case

Pioneer’s published examples bill 80% of the computed cost as a lump sum or 90% over 60 months: on the 1,800-foot example, $3,120 × 0.8 = $2,496 up front, or $3,120 × 0.9 = $2,808 spread over 60 months, which is $46.80 a month. Timing matters at Cherryland: work between December 15 and March 31 adds $3.00 per foot unless the job was inspected, paid and ready before November 1, which would add 800 × $3.00 = $2,400 to the 800-foot example.

Refunds when neighbors connect

If a neighbor later taps a line you paid for, some tariffs send part of your money back.

Keep your extension agreement and tell the utility when a neighbor applies; refunds are rarely automatic.

How to ask for a quote

  1. Confirm the provider. Co-op and investor-owned territories can split along a road.
  2. Ask for the tariff section by name. At APS a single home falls under Schedule 3, section 3, not the subdivision or lot-sale sections.
  3. Submit a site plan and load list. Include panel size and large loads such as electric heat or EV charging; load decides thresholds like Oncor’s 20 kW.
  4. Get the estimate itemized. Total, free and billable feet, rate, credit applied, trimming, rock, tax, and refundability.
  5. Ask about payment plans and timing. Pioneer and Claiborne offer 60-month options, and Cherryland charges more for winter work.
  6. Line up easements early. Versant, Cherryland and Holy Cross all require rights-of-way acceptable to the utility before they build. See how utility easements work for a new home.
  7. Plan for power during construction. The permanent extension is often not energized when building starts, so price temporary construction power for the job site separately.

Then add the customer-side costs and compare lots with the utility connection cost calculator. Related reading: utility extension cost, utility trenching cost, cost to bring utilities to land, gas service line free footage, mobile home utility hookup cost, and the state guides for Texas, Arizona and Colorado.

Frequently asked questions

How many feet of power line does the electric company run for free?

It ranges from none to a quarter mile. Pioneer Electric Cooperative in Kansas builds 1,320 feet free, Kentucky’s rule requires 1,000 feet, NorthWestern Energy in South Dakota builds 500 feet and Oncor in Texas 300 feet overhead. Cherryland Electric in Michigan charges $6.00 per foot from the start.

Does the free footage include the service drop to the house?

It depends on the tariff. Oncor’s 300 feet includes primary, secondary and the service drop. Kentucky’s 1,000 feet excludes the drop from the last pole, so the drop comes on top of the free line.

Is underground line covered by the allowance?

Often only up to the overhead cost. Oncor builds underground free only if it costs no more than 300 feet of overhead line, and Kentucky has the applicant pay the difference between underground and overhead cost.

Will I get money back if my neighbor connects to the line I paid for?

Only if your tariff has a refund or cost-sharing rule. Kentucky refunds the cost of 1,000 feet per directly connected customer for at least 10 years, Holy Cross collects a declining share from the new member. APS, Oncor and Xcel Colorado treat payments as non-refundable.

Can I pay for a line extension over time?

Some co-ops allow it. Pioneer offers a 60-month plan at 90% of the computed cost or a lump sum at 80%, and Claiborne Electric allows up to 60 months at the prime rate plus 5%.

Does the allowance apply to a barn or shop?

Usually not the full residential allowance. Cherryland prices pole barns and garages under a separate auxiliary policy, and Kentucky’s free footage assumes single-phase service of 25 kVA or less.