Concord, NC Water & Sewer Tap and System Development Fees (2026)

Last reviewed: By Utility Cost Guide editor

In Concord, the City of Concord sells water and collects sewer, but the sewer goes on to the Water and Sewer Authority of Cabarrus County (WSACC) for treatment, and each charges a new home separately. On a subdivision lot where the developer’s contractor built the water service, a new single-family home pays $6,023: the City’s $1,632 water system development fee, $264 for a 3/4-inch meter and $1,159 sewer system development fee (City of Concord FY2027 fee schedule, effective August 13, 2026), plus WSACC’s $2,968 wholesale sewer system development fee (WSACC FY2027 SDF schedule, effective July 1, 2026). On an infill lot where Concord installs the water and sewer services from an existing city main, two installation fees add $2,134 and the total becomes $8,157. The caveat most people miss is that these charges come in at two different points. The WSACC fee is collected by Cabarrus County with the building permit, and the City’s charges are paid to Concord. For how this compares nationally, see our guide to the cost to connect to city water.

Concord tap and connection charges at a glance

The table lists every row we verified from the two official schedules, with effective dates and source links. Concord’s residential system development fees (SDFs) are charged per dwelling unit, not by meter size. The water SDF line reads “Per Equivalent Runoff Unit,” the same unit name the schedule uses for stormwater, but its notes apply the fee to each residential unit. The water “installation fee” applies only when Concord installs the service on an existing City-owned main. Where a developer extends a new main and a licensed contractor installs the service, only the meter fee is listed. The WSACC row is a separate agency’s fee for treatment and interceptor capacity, set under North Carolina’s system development fee law (G.S. 162A, Article 8). Deposits and electric rows apply only as their notes describe.

ServiceCategoryFeeMeterAmountBasisEffectiveSourceVerified
Electric — Deposit
ElectricDepositResidential security deposit - electric service—$200flat fee2026-08-13Official source2026-09-24
Electric — Meter
ElectricMeterElectric Meter Base Fee - 200 amp single-phase overhead/underground—$150.42flat fee2026-08-13Official source2026-09-24
Electric — Service Line
ElectricService LineSingle phase primary service installed to a single residential customer—$31.88per linear foot2026-08-13Official source2026-09-24
Sewer — Capacity
SewerCapacityWastewater System Development Fee (SDF) - Multi-Family—$662per unit2026-08-13Official source2026-09-24
SewerCapacityWastewater System Development Fee (SDF) - Single Family—$1,159per unit2026-08-13Official source2026-09-24
SewerCapacityWSACC System Development Fee (wholesale sewer) - 5/8" & 3/4" or Single-Family—$2,968per unit2026-07-01Official source2026-09-24
Sewer — Deposit
SewerDepositResidential security deposit - sewer service—$75flat fee2026-08-13Official source2026-09-24
Sewer — Tap
SewerTapWastewater Installation Fee - 4-inch service—$1,000flat fee2026-08-13Official source2026-09-24
Water — Capacity
WaterCapacityWater System Development Fee (SDF) - Multi-Family—$1,088per unit2026-08-13Official source2026-09-24
WaterCapacityWater System Development Fee (SDF) - Single Family—$1,632per unit2026-08-13Official source2026-09-24
Water — Deposit
WaterDepositResidential security deposit - water service—$75flat fee2026-08-13Official source2026-09-24
Water — Meter
WaterMeterWater Meter Fee - 1" meter1"$395by meter size2026-08-13Official source2026-09-24
WaterMeterWater Meter Fee - 3/4" meter3/4"$264by meter size2026-08-13Official source2026-09-24
Water — Tap
WaterTapWater Installation Fee - 1" meter (installed by Concord Utilities)1"$1,261by meter size2026-08-13Official source2026-09-24
WaterTapWater Installation Fee - 3/4" meter (installed by Concord Utilities)3/4"$1,134by meter size2026-08-13Official source2026-09-24

What a new Concord house pays: worked example

Assumptions: one detached house inside Concord’s water and sewer service area, domestic water only, FY2027 schedules, a 3/4-inch meter (the smallest size on Concord’s schedule) unless noted, and a 4-inch sewer service. The WSACC single-family fee is a flat per-unit charge, so it does not change with meter size.

One-time water and sewer charges for one house, by scenario (sources: City of Concord FY2027 schedule; WSACC FY2027 SDF schedule).

Charge A. Subdivision lot, contractor-built service, 3/4″ B. Infill lot, Concord installs, 3/4″ C. Infill lot, Concord installs, 1″
Concord water SDF (single-family) $1,632 $1,632 $1,632
Water meter fee $264 $264 $395
Water installation fee not listed $1,134 $1,261
Concord sewer SDF (single-family) $1,159 $1,159 $1,159
Sewer installation fee (4-inch service) not assumed $1,000 $1,000
WSACC system development fee $2,968 $2,968 $2,968
Total $6,023 $8,157 $8,415

The arithmetic: scenario A is $1,632 + $264 + $1,159 + $2,968 = $6,023. Scenario B adds the two installation fees: $6,023 + $1,134 + $1,000 = $8,157. Scenario C swaps in the 1-inch meter ($395) and 1-inch installation ($1,261): $1,632 + $395 + $1,261 + $1,159 + $1,000 + $2,968 = $8,415.

Upsizing from a 3/4-inch to a 1-inch meter costs only $258 more in Concord ($131 on the meter, $127 on installation), because the residential SDFs stay flat. That is a very different result from Charlotte, where both SDFs scale with meter size. One gray area deserves a phone call. Concord’s schedule lists the $1,000 sewer installation fee as part of residential wastewater charges, but it does not say whether the fee applies when the developer’s contractor built the lateral. The non-residential table does make that split: it pairs the installation fee with services Concord installs on existing City-owned sewer mains, and lists a connection fee that excludes installation for services installed by others. Scenario A leaves it out. If Concord bills it on your lot, scenario A becomes $7,023.

If your address gets electricity from Concord Electric Systems, the City also requires a City-furnished meter enclosure: $150.42 for a 200-amp single-phase base (FY2027). It is paid by card at the Alfred M. Brown Operations Center and is not included in the totals above.

How Concord compares with Charlotte

Concord’s connection charges are much lower than its larger neighbor’s, especially on infill lots. Using each city’s FY2027 figures, the two common cases compare like this:

Official one-time water and sewer charges, single-family home, FY2027 (Charlotte figures from our Charlotte tap fee page).

Case Concord (3/4″ meter) Charlotte Water (5/8″ meter)
Utility installs water and sewer services $8,157 $17,370
Developer-built services, subdivision lot $6,023 $6,727
Utility installs, 1″ meter $8,415 $29,808

The gap comes from installation: Charlotte Water charges $4,407 for a 5/8-inch water connection and $6,444 for a 4-inch sewer connection, against Concord’s $1,134 and $1,000. On subdivision lots the two are within $704, because the WSACC fee, which has no counterpart in Charlotte Water’s figures, offsets most of Concord’s lower city SDFs.

What is not included in Concord fees

Concord’s and WSACC’s charges cover capacity, the meter and, where Concord installs it, the service to the meter or cleanout. Work on the private side of the connection is priced separately by your contractor:

These ranges come from our national benchmark set and assume normal soil; rock or a street crossing costs more. The guides to water service line cost, sewer lateral cost and utility trenching cost explain what moves each number. Add them to Concord’s official fees here:

Estimate utility connection costs

Estimates are planning figures, not quotes. Confirm fees and trench rules with your utility.

Location and property
Services and site work

Many codes require horizontal separation between water and sewer. This estimate assumes separate water and sewer trenches unless you select a shared run where your utility allows it.

Quoted fees and comparison assumptions

When you pay Concord connection fees

The WSACC fee is due at the building permit stage. Under WSACC’s system development fee ordinance (effective July 1, 2023), the fee is assessed when the building permit is issued. Cabarrus County Building Inspections collects it, and the county will not issue the permit until it is paid (WSACC SDF ordinance). Replacing a mobile home or other structure on the same lot with the same size connection is exempt if the utility confirms the earlier connection in writing.

The City’s charges go to Concord. Where water and sewer already reach the site, you apply for service through Customer Care at 704-920-5555; sites outside city limits need a preliminary application to extend Concord utilities (Concord Utility Availability page). On new main extensions, licensed utility contractors approved by the Water Resources Director do the work, and the meter is bought from the City. The fee schedule also states that no meters will be set in a subdivision until all charges are paid.

Deposits apply only to residential customers without a satisfactory credit rating (see FAQ). Same-day service is not available for meter sets, and we did not find a published installation wait time.

Upcoming changes in Concord

Concord’s current schedule is dated August 13, 2026, and shows the residential sewer SDF as “Starting August 2023.” WSACC’s FY2027 schedule covers July 1, 2026 through June 30, 2027. State law requires the SDF analysis to be updated at least every five years, and WSACC’s 2023 ordinance records an update effective July 1, 2023, which points to the next one by 2028. Check both schedules again if you will pull permits after June 30, 2027.

Common questions about Concord fees

How much are water and sewer tap fees for a new house in Concord, NC?

For FY2027, a single-family home with a 3/4-inch meter pays $6,023 when a contractor built the service in a new subdivision and $8,157 when Concord installs the water and sewer services from an existing main. Both totals include WSACC’s $2,968 sewer system development fee.

What is the WSACC system development fee, and do I have to pay it?

It is a one-time charge for capacity at WSACC’s wastewater treatment plants and interceptor lines. A new single-family home connecting to sewer pays $2,968 in FY2027. Cabarrus County collects it when the building permit is issued, not the City of Concord.

Does a bigger water meter raise Concord’s system development fees?

Not for a single-family home. Concord’s residential water SDF ($1,632) and sewer SDF ($1,159) are per dwelling unit. A 1-inch meter adds only $131 to the meter fee and $127 to the installation fee compared with a 3/4-inch meter.

Why are Concord’s fees lower than Charlotte’s?

Mostly installation charges: $1,134 and $1,000 in Concord against Charlotte Water’s $4,407 and $6,444. On developer-built lots the gap narrows to $704 because Concord homes also pay the WSACC fee.

Do I need a deposit for new utility service in Concord?

Only if you do not meet Concord’s credit standard. Then the deposit is $75 for water, $75 for sewer and $200 for electric, and a credit letter can be used instead.

Is there a fee for the electric meter on a new house?

If Concord Electric Systems serves the address, the City supplies the meter enclosure and charges $150.42 for a 200-amp single-phase base, or $290.42 for 400 amps. Payment is by card at the Alfred M. Brown Operations Center.

Related guides for Concord

Compare Concord with Charlotte and Raleigh on the North Carolina utility connection costs hub, or see the national tap fees by city table. Background: tap fee vs. impact fee, sewer tap fees, water meter installation cost and utility costs for new construction. For a full budget, use the utility connection cost calculator.

Concord fee sources