Leander Water & Wastewater Tap and Impact Fees (2026)

Last reviewed: By Utility Cost Guide editor

Inside Leander, the City of Leander provides both water and wastewater service, and nearly all of the connection cost is the city’s community impact fee (CIF), which it charges under Texas Local Government Code chapter 395. For a new single-family home with a 5/8-inch meter on a lot platted after August 17, 2023, the published charges come to $11,503: a $8,762 water impact fee, a $2,301 wastewater impact fee, a $340 water tap fee for the city to inspect the service line and set the meter, and a $100 wastewater inspection tap fee. A 3/4-inch meter raises that to $17,109.50, because the impact fee scales with meter size. The biggest caveat is the plat date. Leander keeps the impact fee in force when the subdivision plat was recorded, so a house in an older subdivision can owe far less than one on a newly platted lot. For how this compares nationally, see our guide to the cost to connect to city water.

Leander connection fees at a glance

The table below lists every Leander row in our database, each linked to the city code section or city handout it came from. Leander states its impact fee per living unit equivalent (LUE). The code defines one LUE as the water used and wastewater generated by an average single-family detached house, so a standard home with a 5/8-inch meter is 1 LUE. The city’s fee handout converts that to meter sizes: a 3/4-inch meter pays 1.5 times the per-LUE rate and a 1-inch meter 2.5 times. Each tap fee has two versions: a lower one when the developer has already installed the service line and the city only inspects it and sets the meter (the normal case in a new subdivision), and a higher one when city crews install the line. The Liberty Hill rows apply only in that service area.

ServiceCategoryFeeMeterAmountBasisEffectiveSourceVerified
Sewer — Capacity
SewerCapacitySystem reservation fee - Liberty Hill wholesale wastewater service area—$350per equivalent residential unit—Official source2026-09-24
Sewer — Connection
SewerConnectionAdditional connection fee - Liberty Hill lift stations—$1,400per equivalent residential unit—Official source2026-09-24
SewerConnectionWholesale wastewater connection fee - Liberty Hill service area
Liberty Hill area connection fee
—$1,550per equivalent residential unit—Official source2026-09-24
SewerConnectionWholesale wastewater connection fee - Liberty Hill service area (reservation fee paid)
Liberty Hill area, reservation fee already paid
—$1,200per equivalent residential unit—Official source2026-09-24
Sewer — Impact
SewerImpactWastewater Community Impact Fee (CIF)
Platted after Aug 17, 2023
—$2,301per equivalent residential unit2023-08-17Official source2026-09-24
SewerImpactWastewater Community Impact Fee (CIF), 2017 schedule
Platted Oct 2, 2017–Aug 17, 2023
—$2,820by meter size2017-10-02Official source2026-09-24
SewerImpactWastewater Community Impact Fee (CIF), prior schedule
Platted May 3, 2012–Oct 2, 2017
—$1,615per unit2012-05-03Official source2026-09-24
SewerImpactWastewater Community Impact Fee (CIF), 3/4-inch meter3/4"$3,451.50by meter size2023-08-17Official source2026-09-24
Sewer — Inspection
SewerInspectionWastewater tap fee - service line installed, city inspects connection
Lateral installed; city inspects
—$100flat fee—Official source2026-09-24
Sewer — Tap
SewerTapWastewater tap fee - city installs service line
City installs lateral
—$750flat fee—Official source2026-09-24
Water — Deposit
WaterDepositWater deposit—$100per equivalent residential unit—Official source2026-09-24
Water — Impact
WaterImpactWater Community Impact Fee (CIF)
Platted after Aug 17, 2023
—$8,762per equivalent residential unit2023-08-17Official source2026-09-24
WaterImpactWater Community Impact Fee (CIF), 2017 schedule
Platted Oct 2, 2017–Aug 17, 2023
—$4,309by meter size2017-10-02Official source2026-09-24
WaterImpactWater Community Impact Fee (CIF), prior schedule
Platted May 3, 2012–Oct 2, 2017
—$3,880per unit2012-05-03Official source2026-09-24
WaterImpactWater Community Impact Fee (CIF), 3/4-inch meter3/4"$13,143by meter size2023-08-17Official source2026-09-24
Water — Meter Set
WaterMeter SetWater tap fee - service line installed, city inspects and sets meter3/4"$415by meter size—Official source2026-09-24
WaterMeter SetWater tap fee - service line installed, city inspects and sets meter
Service line installed; city inspects and sets meter
5/8"$340by meter size—Official source2026-09-24
Water — Tap
WaterTapWater tap fee - city installs service line and sets meter3/4"$940by meter size—Official source2026-09-24
WaterTapWater tap fee - city installs service line and sets meter
City installs service line
5/8"$840by meter size—Official source2026-09-24

Worked example: a new home in Leander

Assumptions: detached house inside city limits, lot platted after August 17, 2023, and service lines stubbed out by the developer, so the city only inspects and sets the meter. The impact fees are from Sec. 13.07.009 of the Leander Code of Ordinances (Ordinance 23-044-00, August 17, 2023). The tap fees are from Appendix A, Sec. A7.007. The 3/4-inch impact fees are from the city’s Tap & Impact Fees handout for properties platted after August 17, 2023.

Leander water and wastewater charges for one home by meter size. Impact fee = $8,762 water and $2,301 wastewater per LUE.

Line item 5/8-inch meter (1 LUE) 3/4-inch meter (1.5 LUE)
Water community impact fee $8,762.00 $13,143.00
Wastewater community impact fee $2,301.00 $3,451.50
Water tap fee, line installed, city inspects and sets meter $340.00 $415.00
Wastewater tap fee, line installed, city inspects $100.00 $100.00
Total $11,503.00 $17,109.50
Refundable water deposit $100 per LUE $100 per LUE

Adjustments:

What is not included in Leander fees

The city’s charges cover the impact fee, the meter set and the inspection. Work on your side of the connection is private:

National figures are estimates from our benchmark set, not Leander quotes. To combine Leander’s official fees with your own line lengths:

Estimate utility connection costs

Estimates are planning figures, not quotes. Confirm fees and trench rules with your utility.

Location and property
Services and site work

Many codes require horizontal separation between water and sewer. This estimate assumes separate water and sewer trenches unless you select a shared run where your utility allows it.

Quoted fees and comparison assumptions

When you pay Leander connection fees

Upcoming changes in Leander

How Leander compares with Austin and Georgetown

Leander sits between its two neighbors. With a 5/8-inch meter on a lot platted after each city’s 2023 fee update, Austin Water’s published charges come to about $8,119. Leander’s are $11,503. At 3/4 inch the gap widens: Austin is about $11,997 and Leander $17,109.50, because both cities scale the impact fee by meter size. Georgetown charges $24,493.50 at its Phase 2 rates, but counts every standard single-family home as 1.0 service unit regardless of meter size.

Leander tap fee FAQ

How much are Leander’s water and wastewater impact fees in 2026?

For land platted after August 17, 2023, Leander charges $8,762 for water and $2,301 for wastewater per living unit equivalent, or $11,063 for a standard home with a 5/8-inch meter. With a 3/4-inch meter the city’s handout lists $13,143 and $3,451.50, or $16,594.50.

Does a bigger meter really cost more in Leander?

Yes. Leander’s handout sets the impact fee by meter size. A 3/4-inch meter is 1.5 times the 5/8-inch fee, and a 1-inch meter ($21,905 water and $5,752.50 wastewater) is 2.5 times. Moving from 5/8 to 3/4 inch adds $5,531.50 in impact fees plus $75 on the tap fee.

Why is my builder’s impact fee lower than the current rate?

Leander keeps the fee that was in force when the subdivision plat was approved and recorded. City handouts list $4,309 for water and $2,820 for wastewater for lots platted after October 2, 2017 (before the 2023 update), and $3,880 and $1,615 per housing unit for lots platted after May 3, 2012 and before that. Ask the city which schedule matches your plat.

What is the Liberty Hill wastewater service area charge?

Property in Leander’s wholesale wastewater service area is served by Liberty Hill’s treatment plant. It pays a connection fee of $1,550 per LUE at building permit, or $1,200 if the $350-per-LUE reservation fee was paid at preliminary plat. Lots on certain lift stations pay another $1,400 per LUE.

Is the $100 water deposit refundable?

Yes. Sec. A7.001 makes it refundable when service ends. It is $100 per LUE for single-family homes and duplexes.

Related: Texas utility connection costs by city · tap fee vs. impact fee · water tap fees · sewer tap fees · water meter installation cost · Austin fees · Georgetown fees · utility connection cost calculator

Official documents behind the Leander figures