Inside the City of Fresno, the Department of Public Utilities (DPU) provides both water and sewer service, and its connection charges are set in the Public Utilities section of the city’s Master Fee Schedule. A new single-family home on a lot under 20,000 sq ft, with the 1-inch service the schedule sets as the residential minimum, pays about $10,466 in city water and sewer connection charges under the schedule effective July 1, 2026: the $5,686.83 water capacity fee, $2,241 to install the meter and service, the $2,119 wastewater facilities charge and a $419 trunk sewer charge. The key local caveat is that several sewer and water charges depend on the parcel: its trunk sewer area, when its map vested, and whether the lot has already paid for the mains in front of it. For how this compares nationally, see our guide to the cost to connect to city water.

Official Fresno fees in one table

Every row below comes from the DPU pages of the City of Fresno Master Fee Schedule (MFS Amendment #590, fees effective July 1, 2026). They fall into three groups. The water capacity fee and the wastewater facilities sewer charge are the capacity charges, and they make up most of the bill. The meter and service installation charge is the city’s price for making the tap and setting the meter. The rest are location charges (trunk sewer area, lateral sewer, oversize and frontage charges, the Copper Avenue lift station fee) that only some lots pay. The table lists all three capacity-fee meter sizes and all four trunk sewer areas; a home pays one of each.

ServiceCategoryFeeMeterAmountBasisEffectiveSourceVerified
Sewer — Capacity
SewerCapacityWastewater Facilities Sewer Charge (Residential), maps vested after Dec 30, 1995 (Phase 1b)
Maps vested after Dec 30, 1995 (Phase 1b)
—$2,119per unit2026-07-01Official source2026-09-25
SewerCapacityWastewater Facilities Sewer Charge (Residential), maps vested Oct 25, 1992 - Dec 30, 1995 (Phase 1a)
Maps vested Oct 25, 1992 to Dec 30, 1995 (Phase 1a)
—$1,910per unit2026-07-01Official source2026-09-25
Sewer — Connection
SewerConnectionCopper Avenue Sewer Lift Station Benefit Service Area Fee—$650per equivalent residential unit2026-07-01Official source2026-09-25
SewerConnectionLateral Sewer Charge—$0.10per sq ft2026-07-01Official source2026-09-25
SewerConnectionOversize Charge—$0.05per sq ft2026-07-01Official source2026-09-25
SewerConnectionTrunk Sewer Charge (Residential) - Cornelia Service Area
Cornelia trunk sewer area
—$419per unit2026-07-01Official source2026-09-25
SewerConnectionTrunk Sewer Charge (Residential) - Fowler Service Area
Fowler trunk sewer area
—$344per unit2026-07-01Official source2026-09-25
SewerConnectionTrunk Sewer Charge (Residential) - Grantland Service Area
Grantland trunk sewer area
—$419per unit2026-07-01Official source2026-09-25
SewerConnectionTrunk Sewer Charge (Residential) - Herndon Service Area
Herndon trunk sewer area
—$496per unit2026-07-01Official source2026-09-25
Sewer — Inspection
SewerInspectionCCTV Inspection lateral tie-in (sewer mains less than 15 in.)—$130.25varies2026-07-01Official source2026-09-25
Sewer — Tap
SewerTapHouse Branch Sewer Charge (House Branch Connection)—See formulaformula2026-07-01Official source2026-09-25
Water — Capacity
WaterCapacityWater Capacity Fee
1-1/2-inch (lot 20,000 sq ft or more)
1-1/2"$7,109.54by meter size2026-07-01Official source2026-09-25
WaterCapacityWater Capacity Fee
1-inch (residential minimum, lot under 20,000 sq ft)
1"$5,686.83by meter size2026-07-01Official source2026-09-25
WaterCapacityWater Capacity Fee
Up to 3/4-inch
3/4"$3,552.77by meter size2026-07-01Official source2026-09-25
Water — Main Extension
WaterMain ExtensionWater Connection Charge - Frontage Charge—$6.50per linear foot2026-07-01Official source2026-09-25
Water — Meter
WaterMeterMeter Installation (when installed on existing services)1"$330by meter size2026-07-01Official source2026-09-25
Water — Meter Set
WaterMeter SetMeter & Service Installation (when installed together)
1-1/2-inch meter and service
1-1/2"$2,508by meter size2026-07-01Official source2026-09-25
WaterMeter SetMeter & Service Installation (when installed together)
1-inch meter and service
1"$2,241by meter size2026-07-01Official source2026-09-25
Water — Tap
WaterTapService Installation (without meter)1"$2,178by meter size2026-07-01Official source2026-09-25

Worked example for a single-family home in Fresno

Assumptions: a detached house on a vacant lot with no existing city service, a map that vested after December 30, 1995 (so the Phase 1b wastewater facilities charge applies), and a lot whose frontage and lateral sewer charges were already paid when the subdivision was built. The schedule sets the minimum residential service at 1 inch for lots under 20,000 sq ft and 1-1/2 inch for lots of 20,000 sq ft or more. Three cases:

Estimated City of Fresno DPU connection charges, fees effective July 1, 2026

Charge A: 1″ service, Cornelia or Grantland area B: 1″ service, Herndon area C: 1-1/2″ service (lot 20,000 sq ft+), Cornelia or Grantland area
Water capacity fee $5,686.83 $5,686.83 $7,109.54
Meter and service installation $2,241.00 $2,241.00 $2,508.00
Wastewater facilities sewer charge (Phase 1b) $2,119.00 $2,119.00 $2,119.00
Trunk sewer charge (one area) $419.00 $496.00 $419.00
Total $10,465.83 $10,542.83 $12,155.54

A home in the Fowler trunk sewer area pays $344 instead, which brings case A to $10,390.83. A lot whose map vested between October 25, 1992 and December 30, 1995 pays the Phase 1a wastewater charge of $1,910, which is $209 less.

If the lot has not already paid for the mains, the parcel-based charges are added. For a 50-by-100-foot lot (5,000 sq ft), the lateral sewer charge of $0.10 per sq ft comes to $500, the oversize charge of $0.05 per sq ft to $250, and the water frontage charge of $6.50 per front foot to $325. That is $1,075 more, or $11,540.83 for case A. Both per-square-foot charges count lot depth only up to 100 feet. A lot in the Copper Avenue sewer lift station benefit area adds $650 per dwelling unit.

The schedule lists a 3/4-inch water capacity fee of $3,552.77, but it also sets 1 inch as the minimum residential service. Ask DPU which meter size it will assign before you budget with the smaller fee; the difference is $2,134.06.

What is not included in Fresno fees

The city’s service installation includes the tap, service line, corporation stop, curb stop and fittings, and the meter when the two are installed together. The private water line from the meter to the house, the private sewer lateral, any street work by your contractor and the building department’s plumbing permit are extra. If DPU installs the house branch sewer connection, the schedule bills it at contract cost plus 100 percent, plus $10 and 10 percent for inspection. National estimates (methodology), which already include trenching:

City development impact fees are also separate from the utility charges. The Planning and Development section of the same fee schedule lists, per single-family home, a $2,286.13 citywide fire impact fee, a $5,110.55 park fee (facility plus Quimby land fee) and a $762.39 traffic signal mitigation fee, and street impact fees by gross acre. School district fees and PG&E electric and gas service are also outside these totals; we did not collect PG&E’s line-extension figures for this page.

Estimate utility connection costs

Estimates are planning figures, not quotes. Confirm fees and trench rules with your utility.

Location and property
Services and site work

Many codes require horizontal separation between water and sewer. This estimate assumes separate water and sewer trenches unless you select a shared run where your utility allows it.

Quoted fees and comparison assumptions

When you pay Fresno connection fees

The fee schedule sets amounts, not the payment point, so confirm with DPU and the Planning and Development Department when each charge is invoiced for your permit. Two related points are written into the schedule:

For an accessory dwelling unit, the Planning section’s footnotes say ADUs under 750 sq ft are not charged the city’s development impact fees listed there, and larger ADUs pay the multi-family rate. The DPU pages do not include a separate ADU rule for water or sewer charges. California’s rules for utility fees on ADUs are covered in our ADU utility connection fee guide.

What could change in Fresno

Fresno connection fee questions

How much does it cost to connect a new house to water and sewer in Fresno?

City of Fresno connection charges for a new single-family home with a 1-inch service total about $10,466 under the fee schedule effective July 1, 2026, in the Cornelia or Grantland trunk sewer area. A home in the Herndon area pays about $10,543. A lot that still owes lateral sewer, oversize and frontage charges pays more; for a 50-by-100-foot lot that adds about $1,075.

What is Fresno’s water capacity fee?

It is a one-time charge set by meter size: $3,552.77 up to 3/4 inch, $5,686.83 for 1 inch and $7,109.54 for 1-1/2 inch, effective July 1, 2026. It is adjusted every July 1 using a construction cost index.

How much does Fresno charge to install a water meter?

A new 1-inch meter and service installed together cost $2,241, and 1-1/2 inch costs $2,508. If the service line already exists, adding a 1-inch meter costs $330.

What is the wastewater facilities sewer charge?

It is Fresno’s sewer capacity charge for new homes: $2,119 per unit for maps vested after December 30, 1995, or $1,910 for maps vested between October 25, 1992 and December 30, 1995. The trunk sewer charge for the home’s area ($344 to $496 per living unit) is added to it.

Can I spread out the cost of connecting an existing home to city sewer?

Yes. The fee schedule allows existing single-family residences to defer sewer connection charges under Municipal Code 6-305(c), for up to 15 years with interest at 2 percent above the city’s pooled cash rate or the legal maximum, whichever is less. Water connection charges can be deferred on the same basis.

How Fresno compares

Fresno’s city utility charges are lower than those of the two other large California cities we track. In Sacramento, the city’s Department of Utilities charges total about $20,466 for a new home outside the combined sewer area and $23,732 inside it, before any Regional San fees. In San Diego, city and County Water Authority charges come to about $15,274 for a 1-inch by 3/4-inch meter. Fresno’s roughly $10,466 is about half of Sacramento’s lower figure. The comparison covers utility connection charges only; development impact fees, school fees and contractor work are extra in all three cities.